Southtowns Record

SUPPORTING DOCUMENTS-1

Government
Town of Aurora
Board
Town Board
Meeting
Mar 9, 2026
Kind
Agenda packet
Topics
Zoning and land use, Energy and data center siting, Water, sewer and drainage, Public safety, Budget and taxes, Parks and recreation, Roads and traffic

Original document

Same meeting

Text · page 25 of 54

Read the whole document on one page (all 54 pages, each with its own heading)

This document was a scan. Its text was produced by character recognition and may contain errors; check the original for exact wording.

. Upon receiving the information required on the site plan submittal checklist (which is to be
  attached to the site plan review application) and a complete set of plans, drawings, maps,
  surveys and other materials deemed reasonably necessary and appropriate, the Planning Board
  will review and make an initial assessment of materials and notify the applicant of any
  additional materials needed to complete the site plan review. If variations from the submission
  requirements are to be granted, they will be mutually agreed upon by the applicant and the
  Planning Board at this initial consultation. This will be the preliminary stage of the site plan
  review.
 . To further aid in determining public opinion and concerns, an optional public hearing may, but
  need not be, scheduled by the Planning Board within 45 days of receipt of a completed
  application for site planreview.
 . The Planning Board shail act on such an application and notify the Town Board an applicant,
  in writing, of its action, which shall be to recommend either the acceptance or rejection of an
  application or the conditional acceptance of any application or the acceptance of an application
  conditioned upon certain changes in the proposed project or development.
  Final site plan approval or disapproval will be given by the Town Board following its receipt
  of a written recommendation by the Planning Board to approve, disapprove, or approve with
  modification an applicant’s site plan review application. Such a written recommendation shall
  be made by the Planning Board within 60 days of any public hearing heldby the Planning
  Board or the submission of a completed site plan review application to the Planning Board.
. Any time limits set forth herein may be extended by mutual consent of the Planning Board
  and/or Town Board and the applicant to allow all interested parties to comment upon or modify
  any pending proposal. Notwithstanding the above, if the Town Board determines that it is in
  the best interest of the Town to expedite the review and approval or disapproval of a pending
  application, subject to the provisions of this chapter, the Town Board may notify the Planning
  Board of this determination, in which event the Planning Board will make a written
  recommendation to the Town Board to either accept a pending application without change, to
  accept a pending application subject to certain changes, conditions or modifications or to reject
  a pending application within 60 days of the date of the Town Board’s written request.
 . Within 45 days of receiving a recommendation from the Planning Board, and to further aid in
  determining public opinion and concerns, the Town Board shall schedule a public hearing,
  . Within 45 days of, the public hearing, the Town Board shall approve, disapprove or approve
  with modifications an applicant’s final site plan. In the event that the Town Board rules that
  the site plan does not comply with Town standards or regulations or is unacceptable to the
  Town Board for any other reason, then the record of such determination shall be delivered to
  the applicant, including a separate statement setting forth, in as much detail as needed for the
  applicant to understand the basis for such determination, the criteria used by the Twon Board
  and others in the determination of disapproval.
  . Upon approval by the Town Board, a complete final site plan review package will be sent to
  the Code Enforcement Officer after which a building permit will be issued to the applicant if
  he, she, or it complies with all other applicable rules and regulations.
 . All costs incurred by the Planning Board and/or Town Board or other individuals involved in
  the site plan review for consultation fees or other expenses in connection with the review