Southtowns Record

SUPPORTING DOCUMENTS-1

Government
Town of Aurora
Board
Town Board
Meeting
Mar 9, 2026
Kind
Agenda packet
Topics
Zoning and land use, Energy and data center siting, Water, sewer and drainage, Public safety, Budget and taxes, Parks and recreation, Roads and traffic

Original document

Same meeting

Text · page 34 of 54

Read the whole document on one page (all 54 pages, each with its own heading)

This document was a scan. Its text was produced by character recognition and may contain errors; check the original for exact wording.

parks in excess of that which already exists.
  J.  The development and operation of a solar energy system shall not have a significant adverse impact
  on fish, wildlife, or plant species or their critical habitats, or other significant habitats identified by
  the Town of Aurora or other federal or state regulatory agencies.
  K.  Artificial lighting of any solar energy system shall be limited to lighting required for safety and
  operational purposes and shall be shielded from all neighboring properties and public roads.
  L.  Ifthe use of an approved solar energy system which required a special use permit is discontinued,
  the owner or operator shall notify the Building Inspector within 30 days of such discontinuance. If
  a solar energy system is to be retained and reused, the owner or operator shall further inform the
  Building Inspector of this in writing at such time and obtain any necessary approvals within one
  year, otherwise it shall be automatically deemed abandoned.
  M. Any solar energy system to be used strictly for agricultural use purposes in accordance with New
  York State Agriculture and Markets Law may have some of the requitements of this chapter waived
  by the Building Inspector or Town Board,

SECTION 4.  AMENDMENT NO. 2,
Article Il of Chapter 95A, Section 8 of the Code of the Town of Aurora originally adopted on March 13,
2017, is hereby repealed and amended as follows:

SECTION 8. SPECIAL USE PERMIT CRITERIA.
Special use permits issued for utility-scale solar energy systems shall meet the following conditions:

  A.  Maximum lot area: The maximum lot area shall be 15 acres.
  B.  Setbacks, In addition to the setback requirements of the underlying district, any utility-scale solar
  energy system shall adhere to the following setbacks:
  (1) A minimum 100 feet from all property lot lines bordering a residential (R) use district.
  (2) As regulated for accessory structures in the Commercial (C1, C2, and C3) uses in Chapter
  116 of the Town Code.
  G) From public roads and railroads: a minimum of 75 feet from any public road or railroad
  (measured from the road right-of-way or property line).
  (4) From schools, public parks: a minimum of 750 feet from all property lot lines bordering a
  school or public park.
  C.  Maximum overall height. The height of a utility-scale solar energy system shall not exceed 15 feet
  when oriented at maximum tilt,
  D.  There shall only be allowed one utility-scale solar energy systems per lot.
  E.  A utility-scale solar energy system shall adhere to all applicable federal, state, county and Town of
  Aurora laws, regulations, building, plumbing, electrical, and fire codes.
  F.  Development and operation of a utility-scale solar energy system shall not have a significant
  adverse impact on fish, wildlife, or plant species or their critical habitats, or other significant
  habitats identified by the Town of Aurora or other federal or state regulatory agencies.
  G.  The design, construction, operation, and maintenance of a utility-scale solar energy system shall
  prevent the misdirection and/or reflection of solar rays onto neighboring properties, public roads,
  and public parks in excess of that which already exists.
  H.  All structures and devices used to support solar collectors shall be nonreflective and/or painted a
  subile or earth-tone color.
  I.  All transmission lines and wiring associated with a utility-scale solar energy system shall be buried
  or utilize existing overhead transmission line structures and include necessary encasements in