location of any fuel tanks and/or equipment storage areas must be identified on a plan
  by the contractor once the locations have been determined.

  2.  Fertilizers

  Fertilizers will be applied only in the minimum amounts recommended by the
  manufacturer. Once applied, fertilizer will be worked in the soil to limit exposure to
  stormwater. Storage will be in a covered shed. The contents of any partially used bags
  of fertilizer will be transferred to a sealable plastic bin to avoid spills.

  3.  Paints, Paint Solvents, and Cleaning Solvents

  All containers will be tightly sealed and stored when not in use. Excess paint and
  solvents will not be discharged to the storm sewer system but will be properly disposed
  of according to manufacturer's instructions or state and federal regulations.

  4.  Concrete Wastes

  Concrete trucks will be allowed to wash out or discharge surplus concrete or drum wash
  water on the site, but only in either (1) specifically designated diked areas which have
  been prepared to prevent contact between the concrete and/or wash out and storm
  water which will be discharged from the site or (2) in locations where waste concrete
  can be poured into forms to make riprap or other useful concrete products.

  The hardened residue from the concrete wash out diked areas will be disposed of in the
  same manner as other non-hazardous construction waste materials or may be broken up
  and used on site as deemed appropriate by the Contractor. The job site superintendent
  will be responsible for seeing that these procedures are followed.

  All concrete wash out areas will be located in an area where the likelihood of the area
  contributing to storm water discharges is negligible. If required, additional BMPs must
  be implemented to prevent concrete wastes from contributing to storm water
  discharges. The location of concrete wash out area(s) must be identified on a plan by
  the contractor once the locations have been determined. In addition, a standard detail
  on the construction of the concrete wash out shall be included on this plan.

  E.  Solid and Construction Wastes

  All waste materials will be collected and stored in an appropriately covered container and/or
  securely lidded metal dumpster rented from a local waste management company which must be
  a solid waste management company licensed to do business in New York and the Town of Orchard
  Park. The dumpster will comply with all local and state solid waste management regulations.

  All trash and construction debris from the site will be deposited in the dumpster. The dumpster
  will be emptied a minimum of twice per week or more often if necessary, and the trash will be
  hauled to a landfill approved by the NYSDEC. No construction waste materials will be buried on
  site. All personnel will be instructed regarding the correct procedures for waste disposal.

  All waste dumpsters and roll-off containers will be located in an area where the likelihood of the
  containers contributing to storm water discharges is negligible. If required, additional BMPs must
  be implemented, such as sandbags around the base, to prevent wastes from contributing to
  storm water discharges. The location of waste dumpsters and roll-off containers must be
  identified on a plan by the contractor once the locations have been determined.

Multifamily Development
5/26/26
Page 20 of 23