ESCROW AGREEMENT FOR PAYMENT OF MUNICIPAL EXPENSES

  This Agreement, dated ___________ , 2026, is by and between the Town of Sardinia, Erie
County, State of New York, a municipal corporation duly organized and existing under the Laws
of the State of New York with its principal office located at 12320 Savage Road, Sardinia, NY
14134 (the “Town”), and Sardinia East, LLC, a New York Limited Liability Company with its
principal place of business at 101 Summer Street, Second Floor, Boston, MA 02110, and Nexamp
Solar, LLC, a New York Limited Liability Company with its principal place of business at 101
Summer Street, Second Floor, Boston, MA 02110, (the “Applicant”); The Town and the Applicant
may sometimes be referred to herein individually, as a “party” and, collectively, as the “parties.”

  WHEREAS, Applicant has submitted an application to the Town for site plan approval and
related permits for the development of a large-scale battery energy storage project to be located at
VL Genesee Road in the Town of Sardinia, and identified on the Erie County Tax Map as Parcel
No. 309.00-2-3 (the “Project”); and

  WHEREAS, the Applicant has submitted a proposed site plan, an Agricultural Data
Statement, and other documents describing the proposed installation; and

  WHEREAS, pursuant to Article IX of the New York State Constitution, New York
Municipal Home Rule § 10, and Section 115-62F(2)(H) of the Town’s Zoning Code, the Town has
the authority to engage professional consultants, including legal counsel and engineering firms
(the “Firms”), to assist in the review of the application at the Applicant’s expense; and

  WHEREAS, the Town has determined that it requires the assistance of a land use attorney
and an engineering consultant to adequately review the application, ensure compliance with local
laws, and fulfill its obligations under SEQRA as Lead Agency; and

  WHEREAS, Applicant has agreed to enter into this Escrow Agreement to reimburse the
Town for its reasonable and necessary out of-pocket expenses incurred in connection with the
review of the Project.

  NOW, THEREFORE, in consideration of the mutual promises contained herein, the Town
and Applicant agree as follows:

  1.  The Applicant shall reimburse all of the Town’s reasonable and necessary legal,
  engineering, and consultation fees, costs, and expenses incurred in connection with
  the review of the Project. This includes all services required to process the
  application, review the project for compliance with the Town’s Zoning code and
  Battery Energy Storage Systems Law (Local Law No. 2 of 2021), and complete the
  SEQRA process. Applicant shall not be required to reimburse the Town for any legal
  fees associated with litigation arising in connection with the Town’s review process.