Planning Board Regular Meeting, Sep 2, 2026 — Minutes (full text)
Page 1
Town of Hamburg Planning Board Minutes September 2, 2026
Town of Hamburg
Planning Board Meeting
September 2, 2026, Minutes
The Town of Hamburg Planning Board met for a Regular Meeting at 7:00 PM, on
Wednesday, September 2, 2026, Room 7A/7B of Hamburg Town Hall.
REGULAR MEETING
CALL TO ORDER:
The meeting was called to order at 7:02 PM.
PLEDGE OF ALLEGIANCE
Cynthia Gronachan led the meeting attendees in the recitation of the Pledge of
Allegiance.
ROLL CALL
Present: Member Chmura, Member Clark, Member Geraci, Chair
Gronachan, Member Quandt (alternate), Member Ryan, Member
Stewart, Member Zajac
Staff: Joshua Rogers, Planning Department; Planning Board Attorney
Joseph Gogan; Camie Jarrell, Engineering Department
Public Hearing- 7:00 P.M., Hamburg II East ESS, LLC and Hamburg II West ESS,
LLC- Requesting Zoning Board Approval of a Use Variance and Planning Board
Approval for a Change of Use and Site Plan Approval for a Tier 3 battery energy
storage system (BESS) to be located on a 2.7-acre site at 6433 Railroad Avenue
Member Chmura will be recusing herself from this project and Member Quandt will be
filling in.
Jeremy Kauffman, the Project Manager at RIC Energy, appeared on behalf of the
project along with Samantha Parker-Fann the Environmental Project Manager, Sean
Hopkins the project counsel, and Chief Daniel Murray from ESRG.
Mr. Kauffman provided an introduction to the Planning Board. He explained that ESRG
has prepared the Hazard Mitigation Analysis and the Draft Emergency Response Plan
for this project. Chief Murray is a retired New York Fire Department Deputy Chief and
was formally the Chief in charge of Hazmat operations for the NYFD.
1
Page 2
Town of Hamburg Planning Board Minutes September 2, 2026
Mr. Kauffman detailed responses to concerns from the Planning Board’s August 5th
comments:
o Characterization of prior battery fires
▪ Response found on August 19th letter, Section 2, with a full incident
table
o Hazard Mitigation Analysis and the ERP disclaimer
▪ Response found on August 19th letter, Sections 1 and 3; HMA (July
27); draft ERP (July 28)
o Long-term vibration from adjacent rail corridors
▪ Response found on August 19th letter, Section 5
o Nerby residences, churches, schools, and Lake Erie
▪ Response found on August 19th letter, Section 4; Noise Impact
Assessment (July 30)
o Fire-service access, hydrant routing, and mutual aid
▪ Response found on August 19th letter, Section 7; meeting with Fire
Chief and Town staff on August 24th
o Why this site and not another location
▪ ESS feasibility map and parcel-by-parcel analysis, submitted May
3rd
o Input from the railroad companies
▪ CSX and Norfolk Southern formally noticed during coordinated
review; no response received
o Distance to nearby homes and extent of tree clearing
▪ Proximity and Tree Clearing Exhibits, submitted August 27th
o Rare, threatened and endangered species
▪ Habitat Assessment and USFWS species list, submitted August 31 st
Mr. Kauffman also highlighted a presentation, with the following comments:
• The Project at a Glance
o Two facilities. Hamburg II East and Hamburg II West, 4.9 MWac each
(4,896 kW AC), on one parcel.
o Ten Tesla Megapack 2XL units, five per facility.
o Lithium iron phosphate chemistry, selected for thermal stability.
o Fenced equipment area about 14,108 square feet, roughly 0.32 acre, on a
parcel of about 2.7 acres.
o No permanent employees. Monitored remotely 24 hours a day.
o Connects to the existing distribution line on Railroad Avenue.
• Project Location and Existing Conditions
2
Page 3
Town of Hamburg Planning Board Minutes September 2, 2026
o 6433 Railroad Avenue, Lake View, New York 14085 (SBL # 193.00-4-2)
o The parcel sits between two active railroad rights-of-way.
o Dense existing vegetation screens the parcel on all sides
o No wetlands on the parcel; NYSDEC confirmed it has no jurisdiction, and
a 2025 delineation found none.
o Mostly flat topography across roughly 2.7 acres.
• Why This Site
o We screened parcels across the area on interconnection capacity, size,
slope, wetlands, railroad constraints, ownership, and willingness to
transact.
o The feasibility map and parcel-by-parcel analysis were submitted to the
Planning Board on May 3rd.
o Limited frontage, a narrow buildable strip between two rail corridors, and
immediate access to the distribution line.
o The same features make it a poor fit for the homes, shops, schools,
offices, or lodging allowed in Neighborhood Commercial.
o CSX and Norfolk Southern were formally noticed during the coordinated
review. Neither returned comment.
Mr. Murray gave a background on the batteries and the history of the laws.
Chair Gronachan made the following statement:
“A public hearing is an opportunity for the community to share information on how they
are impacted by the project; a three-minute rule will apply. It is not a question-and-
answer period. All statements made during the hearing, as well as written
correspondence regarding the projects, will be sent to the Planning Department to be
reviewed by the Planning Board as well as the applicant.”
Member Geraci read the following Public Hearing Notice:
“Notice is hereby given that the Town of Hamburg Planning Board will conduct a public
hearing on a proposal for a Tier 3 battery energy storage system (BESS) to be located
on a 2.7-acre site at 6433 Railroad Avenue. The Public Hearing will be held on
September 2nd, 2026 at 7:00 p.m. in Room 7A/7B of Hamburg Town Hall.”
Chair Gronachan declared the public hearing open.
Charles Fiorello: Spoke in opposition to the project with the following comments:
• This is in an area that is zoned residential. Why would the residents want to
have the zone changed to commercial or industrial to put this in?
3
Page 4
Town of Hamburg Planning Board Minutes September 2, 2026
• Safety- he feels that the information that has been presented by RIC is only
partially true.
• If there is a fire, the fallout would be deemed very toxic and dangerous both to
the ground soil and homes.
• He provided a printout to the Planning Board for their review.
Timothy Pike: Questions for the Planning Board:
• What is the overall goal of this project?
• Does it fit within a larger Town project?
• What problems does this project solve for residents?
• How does the Planning Board determine these problems?
Rick Schmidt: Spoke in opposition to the project. Stated that he feels this is
inappropriate for a residential neighborhood and that the Planning Board must reject it.
He is worried about the lack of unknown long-term health risks associated with the
potential battery fire as well as the decrease in property values throughout the
neighborhood.
Christine Noonan: With her background in real estate, she wanted to reiterate that
property values will decrease whether there is an issue or not. Due to the current
housing shortage, the Planning Board should be concerned with the fact that the
property values will decrease not only in Lake View but in the surrounding area, as this
has been proven in other areas. Miss Noonan had the following questions for the
Planning Board:
• Why is the monitoring being done remotely? Does that mean no one wants to be
there?
• Why should residents live around that?
• What is the response time?
• Will any type of issue have a longer response time because no one is there
monitoring?
• If no one wants to be on site to monitor the property, why should they live near
the site?
Kathy Moran: Spoke in support of the project. Ms. Moran is a member of Third Act
Upstate New York, which is a grassroots organization advocating rapid clean energy
expansion, stronger climate policies and uplift democracy as well as a member of The
Climate Reality Project. She provided a handout to the Planning Board for them to
review. Energy storage is a smart and reliable technology that helps modernize New
York’s electrical grid, helping to make the grid more flexible, efficient and resilient. This
4
Page 5
Town of Hamburg Planning Board Minutes September 2, 2026
technology is already playing an important role in making electricity in New York
affordable and dependable.
Chris Barton: Spoke in opposition to the project. She feels that batteries have their
place, but not in a residential neighborhood. It is her understanding that RIC has never
build a functioning BESS system in the United States, which leads her to have concerns
about the Planning Boards motivation for consider a project like this from a company
that has no proven track record.
Joyce Culp: Spoke in opposition to the project. Her concerns:
• There is no information regarding evacuation plans for residents as there are
many people that live within a few hundred feet of the proposed site.
• There is information that these fires can burn for days and may even regenerate
several days after they are extinguished causing the surrounding areas to be
unsafe. This would lead the residents to be misplaced for an unknown length of
time.
• Where would the residents be evacuated?
• Who would cover the cost of the evacuation the families would endure?
• Due to the lack of knowledge regarding health concerns, who would cover the
cost of health damage, home damage or work loss caused by exposure to the
chemicals released by high temperature burns?
Colleen Kashino: Spoke in opposition to the project. When she was reviewing the
project she was wondering why there is a distinction between Hamburg II East LLC and
Hamburg II West LLC and after some research she found that they are shell companies
for RIC Energies. When looking into the safety standards she found that if it were a
single LLC, they would have the highest level of safety standards for the neighborhood
in the country. However, because this is two different LLCs she found that they would
have to follow the 2026 National Fire Protection Association Standards instead.
Nila Penfold: Spoke in opposition to the project.
• What are the specific benefits guaranteed for residents, like lower energy costs
and improved grid reliability?
• Will it be enhanced with solar power or wind power?
• Will it provide backup power to our community or be sold back to National Grid?
• Does our neighborhood have a need for stored energy?
• Is there a formal plan for decommissioning this site?
Karen Melisz: Spoke in opposition to the project with the following concerns:
5
Page 6
Town of Hamburg Planning Board Minutes September 2, 2026
• Noise especially since it is just below the Town limit and since it is proposed next
to railroad tracks that are used, it will be an enhancement of noise.
• There is also concern about contamination of the soil, to the surrounding
neighbors, and to the business.
Kim Jablonski: Spoke in opposition to the project.
• Who is ultimately responsible for the development and commissioning of this
project?
• Will the Town/taxpayers ultimately be held financially responsible? If so, which
aspects are the applicant responsible for?
• Will our taxes be used to pay for any of the ongoing costs?
• Will the Planning Board require landscaping to help shield the structure from the
view of immediate neighboring properties?
• From the project details, it does not appear that a fire truck or emergency vehicle
could turn around at this location.
• It is not clear if no more than one truck could enter this location at the same
time?
• Who will cover the cost of meeting New York State Fire Codes at this location?
• Does the Town have employees with the appropriate background to understand
the contractual obligations of an approved BESS?
• Does the Town have current employees with the appropriate experience to verify
all that is needed to construct or monitor this very specialized Battery Energy
Storage System?
• Though they do seem secure, are the systems vandal proof?
• Who is responsible for the additional training and equipment that our firefighters
will need?
• In the case of an emergency, how will it be communicated to the residents?
• How will the monitoring of the system work if there is a loss of internet or Wi-Fi?
Julie Palmer: Spoke in opposition to the project. This project contradicts decades of
land preservation efforts supported by the Town of Hamburg and the residents of Lake
View. Although she does understand that this facility may contribute to the statewide
green energy goals, she does not see that there is a direct benefit to the local Lake
View community.
Dan Judd: Spoke in opposition to the project. As a retired New York Licensed Civil
Engineer, he finds many of the comments regarding the vibration and the railroads
laughable. The main railroad corridor that runs through Lake View is highly active and
for that reason he feels that a battery storage system should not be located next to them
due to the following engineering and safety risks:
6
Page 7
Town of Hamburg Planning Board Minutes September 2, 2026
• Vibration damages- heavy freight and passenger trains produce constant and
intense ground vibrations which affect the physical integrity of the sensitive
battery and electronic components which cause short circuits (which is the
leading cause of thermal runaway or fires).
• Derailment impact- a train derailment could physically breach the battery
containers triggering a thermal runaway, explosion or toxic chemical releases.
• Access obstructions- freight trains can block roadways and site access for hours
preventing rapid emergency response and maintenance crews from reaching the
facility during a battery fire.
• Flying debris- trains can throw ballasts, rocks, cargo fragments to name a few.
The high-speed debris can severely damage the outer casing of the BESS units
• Electromagnetic Interferences- train signal networks generate intense
electromagnetic fields. This can interfere with the hypersensitive electronics
inside the BESS particularly its battery management systems.
Debbie Kaczmarski: Spoke in opposition to the project and reiterated the previous
statements.
Kimberly Catalano-Pike: Spoke in opposition to the project and reiterated the previous
statements.
Father Sean De Maria Judd: Spoke in opposition to the project and reiterated the
previous statements.
Noah Fuchs: Spoke in opposition to the project and reiterated the previous statements.
Chair Gronachan declared the public hearing closed.
Chair Gronachan reiterated that if there was any other additional information that the
public would like to present to the Planning Board, to please send letters and/or emails
to Joshua Rogers.
The project was then tabled to the September 16th , 2026 Planning Board meeting.
Public Hearing- 7:00 P.M., Dave Manko- Requesting Amended Site Plan Approval
of revised dumpster locations for the Mission Hills Villas Phase IV project, located
on the east side of Camp Road
Member Geraci read the following Public Hearing Notice:
“Notice is hereby given that the Town of Hamburg Planning Board will conduct a public
hearing on a proposal for an amended site plan approval of revised dumpster locations
7
Page 8
Town of Hamburg Planning Board Minutes September 2, 2026
for the Mission Hills Villas Phase IV project, located on the East side of Camp Road.
The Public Hearing will be held on September 2nd, 2026, at 7:00 p.m. in Room 7A/7B of
Hamburg Town Hall.”
Chair Gronachan declared the public hearing open.
No one spoke.
Chair Gronachan declared the public hearing closed with no comment provided.
Town Engineer Camie Jarrell stated that an engineering letter dated August 27, 2026,
was written that states that there are no engineering comments.
Mission Hills Villas Phase IV Revised Dumpster Locations
4543A Camp Road
SEQRA and Approval Resolution
September 2, 2026
SEQR
Whereas, The Hamburg Planning Board received a new site plan requesting amended
Site Plan Approval of revised dumpster locations for Phase IV of the Mission Hills
project at 4543A Camp Road (SBL #:170.07-2-1.11), which was originally approved in
2023; and
Whereas, the Town of Hamburg Planning Board held the required public hearing on
September 2nd, 2026; and
Whereas, The Mission Hiss project was the subject of an EIS and Findings were issued
by the Town; and
Whereas, the Planning Board reviewed the SEQR Findings and has determined that
the project, which is in substantial accordance with the original site layout, is in
accordance with SEQR Findings.
Now, Therefore, Be it Resolved, that the Town of Hamburg Planning Board hereby
determines that the SEQR Negative Declaration issued previously is still valid.
Motion made by Member Chmura, with a second from Member Ryan.
Resolution passes with no opposition.
Approval Resolution
8
Page 9
Town of Hamburg Planning Board Minutes September 2, 2026
The Planning Board hereby grants conditional Site Plan approval for revised dumpster
locations for Phase IV of the Mission Hills project to be located at 4543A Camp Road
(SBL #: 1740.07-2-1.11) with the following conditions and waivers:
1. Approval is contingent upon the Engineering Department comment letter dated
8/27/2026.
Motion made by Member Chmura, with a second from Member Ryan.
Resolution passes with no opposition.
Public Hearing- 7:00 P.M., Mike Sweeney- Requesting Site Plan Approval on a
proposal for a 55,000 sq-ft industrial storage building on an existing asphalt-
gravel storage yard to be located at 3100 Lakeshore Road (SBL #:150.00-1-1.2)
Thomas Shelberg of DEL Resources appeared on behalf of the project along with Mike
Sweeney.
Mr. Rogers explained that the coordinated review comment period for SEQR will
technically end on Friday September 4th, 2026. However, comments have been
received from pretty much every major agency that has been contacted. None of the
major agencies had any major concerns that were shared and Erie County had no
recommendation.
Mr. Rogers detailed that the coordinated review package was sent to the Department of
Conservation, NYSDOT, Erie County, and the Town of Hamburg Local Waterfront
Revitalization Program (LWRP) Committee.
The Town of Hamburg’s LWRP Committee reviewed the project and issued a positive
recommendation which has been provided to the members.
Member Geraci read the following Public Hearing Notice:
“Notice is hereby given that the Town of Hamburg Planning Board will conduct a public
hearing on a proposal for a 55,000 sq-ft industrial storage building on an existing
asphalt-gravel storage yard to be located at 3100 Lakeshore Road (SBL#: 150.00-1-1.2)
The Public Hearing will be held on September 2nd, 2026, at 7:00 p.m. in Room 7A/7B of
Hamburg Town Hall.”
Chair Gronachan declared the public hearing open.
No one spoke.
Chair Gronachan declared the public hearing closed with no comment provided.
9
Page 10
Town of Hamburg Planning Board Minutes September 2, 2026
Chair Gronachan asked if board members had any additional questions for the applicant
or is the board in favor of moving forward?
Member Chmura stated she is in favor of moving forward as she feels that the applicant
has addressed all comments and responses from agencies.
Member Stewart and Geraci agreed.
Chair Gronachan requested the Planning Department draft Part 2 and Part 3 of the Full
Environmental Assessment Form (FEAF) for consideration by the Planning Board and
the drafting of approval resolutions for the next meeting.
The project was then tabled to the September 16, 2026 Planning Board meeting.
M&T Bank- Requesting Site Plan Approval on a proposal for a drive-up ATM kiosk
to be located at 6000 South Park Avenue
Stephen Movalli from Scheid Architectural appeared on behalf of the project along with
Sandy Mancuso from M&T Bank.
Mr. Movalli provided background for the Planning Board. They are seeking Planning
Board approval for a drive-up ATM kiosk to be located in the parking area behind the
branch to give the customers additional ATM access. Mr. Movalli explained the project
meets Town requirements for stacking and has no impact on stormwater or parking. It is
an ATM, a clearance pole, and a light pole so that it meets the ATM Safety Act
requirements.
Mr. Rogers explained a project like this normally would not come before the Planning
Board. However, the reason it is before the Board is due to past precedent where
everything in the plaza next to the Town Hall has come before the Planning Board. From
a Planning Department standpoint, there are no issues. It will be a Type II Action under
SEQRA with no environmental impacts. If the Planning Board is comfortable, it can be
scheduled for a public hearing on September 16th, 2026, and can authorize approval
resolutions for the same meeting.
No objections were presented and approval was given for the Planning Department to
draft approval resolutions.
The project was then tabled to the September 16, 2026 Planning Board meeting.
10
Page 11
Town of Hamburg Planning Board Minutes September 2, 2026
A.K. Kaid- Requesting Change of Use and Site Plan Approval on a proposal for a
retail cannabis dispensary and associated site improvements to be located at
3233 Lakeshore Road
Tommaso Briatico of Tommaso Briatico Architects appeared on behalf of the project.
Chair Gronachan stated at the last meeting, the Planning Board was strict about closing
off the garage door and removing the patio. On September 2, 2026, the Planning Board
received an email saying that the patio will not be removed.
Chair Gronachan stated that she felt that this case should be tabled until the applicant
decides what they are going to do.
Member Chmura reiterated that it was very clear the patio, regardless of trying to have
architectural input and revitalize the corner, ends up encouraging on site congregation
which would in turn end up encouraging on site consumption. She added that this is not
that type of institution, and moreover, it is against the law to have on -site consumption.
Member Chmura stated it is disrespectful to the Planning Board that after multiple
meetings and them being very clear to remove it, the patio is still in the drawings. If the
applicant wants to have a trellis, they can put it over the doorway. There is no need for it
to be on the side of the building that would then create a deck leading to a space for
congregating.
Mr. Briatico explained it was not trying their intent to be disrespectful, and the reasoning
behind the trellis was to improve the façade and entrance making it more inviting. He
stated they do understand that if the Planning Board wants it removed, they must
comply. This is just a conceptual drawing and will be taken out.
Chair Gronachan added that the Planning Board also requested further explanation on
the security system.
Mr. Briatico explained there will be eight (8) cameras inside the store as well as eight (8)
cameras outside. There will be a 24-hour monitoring system as required that is being
backed up and covered by a third-party service.
Chair Gronachan clarified the question was regarding the monitoring; she asked will it
be going through an agency?
Mr. Briatico answered yes, the Applicant is going to hire a third-party agency to monitor
it 24 hours a day since when people leave, the premises must still be monitored.
Member Zajac said the Applicant stated that it will be a 30-day retention period for the
video, an clarified that New York State Law is 60 days.
11
Page 12
Town of Hamburg Planning Board Minutes September 2, 2026
Mr. Briatico responded that New York State has requirements that if they are not
complied with, New York State will revoke your license to operate. He reiterated the
Applicant will follow New York State Law.
Member Zajac also added that part of New York State Law is that someone will be
checking IDs to verify that no one under the age of 21 is in the building. He asked will
there be a security officer on the premises?
Mr. Briatico responded yes, there will be someone checking IDs.
The project was then tabled to the September 16, 2026 Planning Board meeting.
OTHER BUSINESS
Member Stewart made a motion, seconded by Member Zajac, to approve the following
minutes:
August 5, 2026
As the vote on the motion was seven (7) ayes and one (1) abstention from Member
Chmura - the motion carried.
Member Chmura made a motion, seconded by Member Ryan, to approve the following
minutes:
August 19, 2026
As the vote on the motion was seven (7) ayes and one (1) abstention from Member
Geraci - the motion carried.
Member Chmura made a motion, seconded by Member Ryan, to adjourn the meeting.
The motion carried.
The meeting was adjourned at 9:10 P.M.
Respectfully submitted,
August Geraci, Secretary
12