Southtowns Record

TBA11.09.2026packet

Government
Town of West Seneca
Board
Town Board
Meeting
Nov 9, 2026, 6:00 p.m.
Posted by publisher
Nov 6, 2026
Kind
Agenda packet
Topics
Budget and taxes, Water, sewer and drainage, Public safety, Parks and recreation, Roads and traffic, Zoning and land use, Audits and oversight

Original document

Same meeting

Text · page 8 of 252

Read the whole document on one page (all 252 pages, each with its own heading)

WEST SENECA COURT ROOM  DRAFT TOWN BOARD
1250 Union Road  2026 - 20 Meeting Minutes
West Seneca, NY 14224  October 26, 2026

the appropriate benefits which would be due his family. On behalf of the West Seneca Police
Department and the Town of West Seneca, our thoughts are with the Windover family at this difficult
time.

Ayes: 4  Noes: 0  Abstain: 0  Motion Carried

12. Highway Superintendent Adams re Promotion of Matthew Bauer - Full-Time Sanitation Laborer

Motion by Supervisor Dickson, seconded by Councilmember Robertson, to promote Matthew Bauer
from a Part Time Sanitation Laborer to a Full Time Sanitation Laborer at a rate of $25.30 per hour per
the Blue Collar Contract effective October 26, 2026, to be paid from the Sanitation full time account
line 001-8160-0144-0000-0000.

Ayes: 4  Noes: 0  Abstain: 0  Motion Carried

2. FOR DISCUSSION
1. Town Engineer re Sanitary Sewer Overflow Update

Town Engineer Foote provided the following sanitary sewer overflow update:

Please find attached a chart summarizing the individual and total sanitary sewer overflow volumes
from 2022 through year-to-date 2026. As shown, the Town has made substantial progress in
reducing overflow volumes, with the most significant improvement occurring at the West Seneca
West Bus Garage location, where reported overflow volumes have decreased by more than 80%.

The Town is planning to install flow meters on the discharge piping for the Bus Garage and Plant 5
overflow pumps to provide more accurate measurements of overflow volumes. Additionally, level
controls will be installed at the Bus Garage to automatically start and stop the pumps based on
system conditions, helping to prevent unnecessary bypass pumping.

The Town also plans to upgrade the flow meters where sanitary sewers within Sewer District No. 12
discharge into the Erie County trunk sewer. These improvements are intended to eliminate inaccurate
flow readings caused by surcharging conditions within the County's sewer system. The flow meter
installations and upgrades are anticipated to take place this winter and next spring.

Finally, the Town is planning to upgrade its SCADA system and integrate the various flow meters into
a centralized platform, allowing data to be collected, monitored, and accessed remotely.

Collectively, these improvements will enhance the accuracy and reliability of flow and overflow data,
improve system monitoring and operational efficiency, and provide the Town with better information
to evaluate system performance and prioritize future sanitary sewer improvements.

Supervisor Dickson asked that the chart be added to the town's website. Mr. Foote confirmed the
chart would be uploaded.

Councilmember Sherman asked if the improvements would provide better data. Mr. Foote stated the
SCADA system is a central location for data and provides real-time information.