Southtowns Record

Town Board Regular Meeting Agenda, Nov 16, 2026 — Agenda

Government
Town of Hamburg
Board
Town Board
Meeting
Nov 16, 2026
Kind
Agenda
Topics
Zoning and land use, Water, sewer and drainage, Budget and taxes, Roads and traffic, Public safety, Parks and recreation, Audits and oversight, Short-term rentals

Original document

Text · page 38 of 94

Read the whole document on one page (all 94 pages, each with its own heading)

Real Estate Development | Construction Management

November 12, 2026

Mr. Jeffrey Skrzypek
Supervising Code Enforcement Officer
Town of Hamburg Building Department
S-6100 South Park Avenue
Hamburg, NY 14075

RE:  5272 South Park Avenue, Hamburg, NY 14075
  Demolition Scope of Work and Mobilization Commitment

Dear Mr. Skrzypek:

Thank you for meeting with our team on site on Monday, November 9, 2026. We appreciate the Town's time
and guidance regarding the condition of the existing structures on the campus. This letter confirms the scope
of work discussed at that meeting and our schedule for mobilization.

Sinatra Development is currently in negotiations with two qualified demolition contractors to perform the
following scope of work:

  1.  Demolition of the chapel.
  2.  Demolition of the two hallway wings off the rear of the building, with all resulting openings boarded
  up and secured against weather and unauthorized entry.
  3.  Demolition and removal of the greenhouse at the rear of the property.

This scope is based on the items reviewed during our November 9 meeting. In our communications with the
demolition contractors, we have relayed our understanding from that meeting that the Town will issue a
letter of condemnation for all structures on the property. We would appreciate receiving that letter at your
earliest convenience, as it will allow us to finalize contractor pricing, sequencing, and permitting.

Upon execution of a contract with the selected demolition contractor, we will submit all required demolition
permit applications, contractor insurance certificates, and supporting documentation to your office.

Sinatra Development is committed to mobilizing on this project no later than December 31, 2026. We will
keep your office informed as contractor selection is finalized and will provide a detailed start date and
schedule once available.

Should you have any questions or require additional information, please contact us at 716.220.8468 ext. 7.
Respectfully,

Sinatra Development Company

  Buffalo Headquarters · 617 Main Street, Suite 350 · Buffalo, NY 14203
  Tampa Bay Office · 2502 N. Rocky Point Drive, Suite 520 · Tampa, FL 33607
  716.220.8468 · sinatradev.com
  38