Capital Projects
  Waterline Replacements - Phase 1
  Account Number  Account Description  Project Budget  Current Yr Rev/Exp  Total Project Rev/Exp % Complete
Revenue
H04-2401-0000-0000  INTEREST & EARNINGS  $  -  $  8,987  $  99,920
  $  -  $  8,987  $  99,920
Expenditure
H04-8340-0200-0000  WATERLINE REPLACEMENTS - PHASE 1
  Construction  $  2,415,741  $  265,717  $  2,407,314  99.65%
  Engineering  355,000  4,770  354,610  99.89%
  Advertisment for Bids  -  -  466
  Permit Fees  -  110  220
  $  2,770,741  $  270,597  $  2,762,610

  Town of Boston Comprehensive Plan Update
  Account Number  Account Description  Project Budget  Current Yr Rev/Exp  Total Project Rev/Exp % Complete
Revenue
H05-2706-0000-0000  GRANTS FROM LOCAL GOVT  $  25,000  $  25,000  $  25,000
H05-3097-0000-0000  STATE AID CAPITAL PROJECTS  $  63,000  $  -  $  63,000  100.00%
H05-5031-0000-0000  INTERFUND TRANSFERS  $  6,870  $  -  $  7,000  101.89%
  $  94,870  $  25,000  $  95,000
Expenditure
H05-8020-0200-0000  COMPREHENSIVE PLAN UPDATE  $  94,870  $  -  $  94,870  100.00%
H05-9901-0900-0000  TRANSFER TO OTHER FUNDS  $  -  $  130  $  130
  $  94,870  $  130  $  95,000

  Town Hall Generator
  Account Number  Account Description  Project Budget  Current Yr Rev/Exp  Total Project Rev/Exp % Complete
Revenue
H06-2401-0000-0000  INTEREST & EARNINGS  $  -  $  -  $  4,655
H06-5031-0000-0000  INTERFUND TRANSFERS  -  -  276,439
  $  -  $  -  $  281,094
Expenditure
H06-1620-0200-0000  TOWN HALL GENERATOR
  Construction  $  253,546  $  -  $  253,546  100.00%
  Engineering  20,000  -  20,000  100.00%
  Advertisment for Bids  -  -  732  100.00%
  National Fuel Hookup  -  -  6,816
  $  273,546  $  -  $  281,094

  Town Hall Entryway
  Account Number  Account Description  Project Budget  Current Yr Rev/Exp  Total Project Rev/Exp % Complete
Revenue
H07-2401-0000-0000  INTEREST & EARNINGS  $  -  $  -  $  33
H07-5031-0000-0000  INTERFUND TRANSFERS  64,125  -  59,760
  $  64,125  $  -  $  59,793
Expenditure
H07-1620-0200-0000  TOWN HALL ENTRYWAY
  Construction  $  46,525  $  -  $  41,625  89.47%
  Engineering  17,600  -  17,600  100.00%
  Advertisment for Bids  -  -  568
  $  64,125  $  -  $  59,793

  Fuel Tank Replacement
  Account Number  Account Description  Project Budget  Current Yr Rev/Exp  Total Project Rev/Exp % Complete
Revenue
H08-5031-0000-0000  INTERFUND TRANSFERS  -  -  417,691
  $  -  $  -  $  417,691
Expenditure
H08-1620-0200-0000  FUEL TANK REPLACEMENT - NEW FUEL ISLAND
  Engineering (Res. 2025-26)  64,020  28,830  64,020  100.00%
  Removal  $  75,560  $  10,949  $  71,620  94.79%
  Mis. Exp. - Bidding / Paving Open Ground  -  104  3,723
  Construction  293,000  280,892  280,892  95.87%
  $  432,580  $  320,774  $  420,254

  Holiday Lights
  Account Number  Account Description  Project Budget  Current Yr Rev/Exp  Total Project Rev/Exp % Complete
Revenue
H09-5031-0000-0000  INTERFUND TRANSFERS  -  -  12,500
  $  -  $  -  $  12,500
Expenditure
H09-1440-0200-0000  ENGINEERING - HOLIDAY LIGHTS  $  12,500  $  1,416  $  10,625  85.00%
H09-8297-0200-0000  UTILITIES, OTHER - CAPITAL OUTLAY  $  140,500  $  95,380  $  95,380  67.89%
  $  153,000  $  96,796  $  106,005

  Waterline Replacements - Phase 2
  Account Number  Account Description  Project Budget  Current Yr Rev/Exp  Total Project Rev/Exp % Complete
Revenue
H10-2401-0000-0000  INTEREST & EARNINGS  $  -  $  -  $  1,794
  $  -  $  -  $  1,794
Expenditure
H10-1440-0200-0000  ENGINEERING - WATER PHASE 2  $  991,130  $  400,684  $  429,580  43.34%
H10-8340-0200-0000  WATERLINE REPLACEMENTS - PHASE 2  $  -  $  89,398  $  89,398  100.00%
  $  991,130  $  490,082  $  518,978