Southtowns Record

March 4 2026 Town Board Agenda Packet

Government
Town of Evans
Board
Town Board
Meeting
Mar 4, 2026
Kind
Agenda packet
Topics
Public safety, Zoning and land use, Budget and taxes, Audits and oversight, Water, sewer and drainage, Roads and traffic

Original document

Same meeting

Text · page 11 of 19

Read the whole document on one page (all 19 pages, each with its own heading)

This document was a scan. Its text was produced by character recognition and may contain errors; check the original for exact wording.

RESOLUTION —-APPROVAL OF CHANGE ORDERS FOR SENIOR CENTER WINDOW
PROJECT

WHEREAS, the Town of Evans and Catalano Contracting entered into a contract, per an
awarded bid, to complete the Town of Evans Senior Center window project:

WHEREAS, the following fourteen (14) change orders totaling to the amount of $50,496.77 (see
below):

#1  8/20/2025  Louvers  $ 1,050.00  $ 157.50  $ 1,207.50
#2  9/4/2025  Cabinet Demo  $ 1,200.00  $ 180.00  $ 1,380.00
#3  9/17/2025  Window Janm/Sills  $ 4,022.00  $ 603.30  $ 4,625.30
#4  9/17/2025  Plenum Boxes  $ 5,629.25  §  .00  $ 5,629.25
#5  wee ae  —  —  $  .00
#6  9/17/2025  Mats  $  .00  $  .00
#7  9/22/2025  Grates  -$ 1,600.00  $  00  =-$ 1,600.00
#8  9/22/2025  Oval Window  $  .00  $  .00
#9  9/22/2025  Oval Window  $  .00  $  .00
#10  11/25/2025 Cabinet Carpentry  $ 1,200.00  $ 180.00  $ 1,380.00
#11  12/1/2025  Interior Window Trim $ 9,215.00  $1,382.25  $10,597.25
  (Material)
#12 = 12/1/2025  Gym Framing  $ 6,261.00  $ 939.15  $ 7,200.15
#13  2/23/2025  interior Window Trim $15,900.00  $2,385.00  $18,285.00
  (Labor)
#14  = 2/23/2026  Additional Bonding  $ 1,558.54  $ 233.78  $ 1,792.32

  TOTAL  $50,496.77;

WHEREAS, the $10,000 contingency was utilized to reduce the total increase to $40,496.77;

NOW, THEREFORE, BE IT RESOLVED, the Town of Evans Board authorizes the fourteen (14)
change orders, which increases the above referenced project by $40,496.77 to a total of
$484,088.78.

ROLL CALL VOTE:

ROLL CALL VOTE: