Water Projects Summary
  • Completed! BAN renewed for $987,000 after 1st principal
 Water Tank Refurbishment  payment in October 2024

CDBG Work – Boston State Rd  • Complete! Final payment issued in 2024

  • Bid Awarded for $2,415,741 in August 2024
  • BAN Issued October 2024 for $2,771,000
Phase 1 – District 1 Waterlines  ($2,415,741 construction + $355,259 engineering costs)
  • Construction to start late 2024 / early 2025
  • Updated engineering cost estimate in 2023
Phase 2 – District 1 Waterlines
  • Revised the Bond Resolution in 2023
  & Pump Station Repairs
  • Applied for WIIA funding for the 4th time in 2024
  • Updated engineering cost estimate in 2023
Phase 3 – District 2 Waterlines  • Revised the Bond Resolution in 2023
  • Applied for WIIA funding for the 4th time in 2024
  • Options – Full town / just current districts
  • Options – Unit Based or Ad Valorem
  • Current Debt: (Dist. 3 Bonds + Water Tank BAN) $ 4,654,940
Water District Consolidation &
  • Anticipated Debt (Phase 1-3):  $15,653,466
  Buildout Options
  • Buildout – District 2:  $11,310,000
  • Buildout – South Central:  $12,560,000
  • Buildout – Southeast:  $ 6,600,000  169