Southtowns Record

2025 Town of Boston - Budget Presentation

Government
Town of Boston
Posted by publisher
Oct 1, 2026
Kind
Budget
Topics
Budget and taxes, Water, sewer and drainage, Public safety, Zoning and land use, Parks and recreation, Roads and traffic, Audits and oversight

Original document

Text · page 188 of 204

Read the whole document on one page (all 204 pages, each with its own heading)

Town Hall Generator – Change Order
CCN02 – Abandon the existing electrical feeders and run entirely new from
the pole as shown. The electrical feeders would be directionally drilled
underneath the existing driveway into the new manhole.
Positives for this scenario are:
a. The entire circuit from Pole to building would be replaced. The existing
  feeder that would remain (as designed and under CCN03) from pole to
  manhole would be 1977 vintage. If we proceeded with this scope of
  work now, the Town could avoid a new project later to replace the
  existing section of cables (and have to dig anything back up). That
  would save on design/review time (by engineer/contractor),
  mobilization, inflated cost of material, etc.
b. Minimized electrical shutdown time. This work would probably require
  a few hours of electrical shutdown to complete.
c. Fewer unknowns. Doesn’t require additional excavation. Doesn’t rely
  on reuse of the feeders and their unknown condition.

Negatives for this scenario are: Cost is $34,364.93

CCN03 – Attempt to intercept the existing feeders near the south light post
at the sidewalk/entrance to the building. Excavation would be completed
as carefully as possible not to disturb the curb, asphalt, sidewalk and/or
stairs. Once the feeders have been located, they would be disconnected
from within the building and pulled back to the excavation location. The
existing feeders would then be routed to the new manhole location where
they would splice into the new section of feeders.
Positives for this scenario are:
a. The Cost. $16,025.13…if everything goes well (see below).

Negatives for this scenario are:
a.  We would be banking on the ability to pull the existing feeders back
  and not damaging them in the process. If they are damaged, new
  feeders would then need to be pulled from the pole. (Cost not
  included)
b.  Involves creating a small/tight excavation as to minimize damage to
  driveway and adjacent concrete. (I have asked IPL to define the
  limits of assumed excavation so that we could assess and
  determine additional costs, if necessary)
c.  Longer shutdown time. This work would probably require a 2-day
  electrical shutdown. IPL’s cost does not include a temporary
  generator for this time, if necessary. (I have asked IPL for this cost).
d.  Disturbance to existing planter bed. Would potentially require Parks
  staff to remove/replace plantings.  200