Water Line Replacements – Phase 1 (Sept 2022 updated costs) In one year, cost estimate rose from $3,836,370 to $5,188,005 (up $1,351,635) Current Status: • In Engineering design stage • Hoping to get DOH/ECWA approvals late 2022/early 2023 • Hoping to go out to bid in February/March 2023 • Construction summer of 2023 (pending supply chain issues) Financing: • WIIA – 2021 application denied. Applied again in Sept 2022 • ARPA – Will use any left‐over funds not applied to prior projects • BAN (Bond Anticipation Note) – will go out to financing after bids received. Bond Resolution from November 2021 initiated this 121