TOWN  OF  BOSTON

  TOWN  OF BOSTON - RESOLUTION NO. 2025 - 91

 RESOLUTION APPROVING ENGINEERING SERVICES PROPOSAL FOR PHASE 2
  WATER SYSTEM IMPROVEMENTS

  WHEREAS, the Town of Boston (“Town”) is undertaking the Phase 2 Water System
Improvements Project (the “Project”) to replace approximately 23,115 linear feet of 8-inch and
12-inch water mains, install a new 6,900 linear foot 12-inch transmission main under Route 400 .
at Polish Hill Road, and perform related appurtenant improvements in anticipation of converting
existing Lease-Managed areas of the Town’s water system to Direct Service with the Erie County
Water Authority (ECWA); and

  WHEREAS, CPL, a professional engineering firm, has submitted a proposal dated
October 7, 2025 to provide engineering design, permitting, bidding, construction administration,
and inspection services for the Project; and

  WHEREAS, the proposed scope of services includes preliminary and final design,
permitting and approvals, bidding phase services, construction administration, resident inspection,
and project closeout, for a total proposed fee of $991,130, which represents approximately 14.2%
of the estimated construction cost of $7,000,000 and is consistent with the Phase 1 project fee
percentages; and

  WHEREAS, the Town Board has reviewed the proposal and determined it to be in the
best interest of the Town to retain CPL for the engineering services associated with the Project.

  NOW, THEREFORE, BE IT

  RESOLVED, that the Town Board of the Town of Boston hereby approves the CPL
proposal dated October 7, 2025 for engineering services related.to the Phase 2 Water System
Improvements Project at a total not to exceed fee of $991,130, as more fully set forth in said
proposal; and be it further °

  RESOLVED,  that the Town  Supervisor is hereby  authorized to execute the EJCDC
Standard Form  of Agreement  Between  Owner  and Engineer,  consistent with the terms of the
proposal and in a form approved by the Town Attorney.