Southtowns Record

2021-64-Bond-Resolution

Government
Town of Boston
Posted by publisher
Sep 30, 2026
Kind
Other
Topics
Water, sewer and drainage, Budget and taxes

Original document

Text · page 7 of 7

This document was a scan. Its text was produced by character recognition and may contain errors; check the original for exact wording.

NOTICE
 The resolution, a summary of which is published herewith, has been adopted
  on the 3rd day of November,
 2021. The validity of the obligations authorized by such resolution may be hereafter
  contested only if
 such obligations were authorized for an object or purpose for which the Town of Boston,
  in the County of
 Erie, New York, is not authorized to expend money or if the provisions of jaw
  which should have been
 complied with as of the date of publication of this notice were not substantially
  complied with, and an
 action, suit or proceeding contesting such validity is commenced within twenty days
  after the date of
 publication of the notice, or such obligations were authorized in violation of
  the provisions of the
 constitution.

  SANDRA QUINLAN
  Town Clerk

  BOND  RESOLUTION  OF THE TOWN  OF BOSTON,  NEW  YORK,
  ADOPTED NOVEMBER 3, 2021, APPROPRIATING $1 1,058,000 FOR THE
  COST OF AN INCREASE AND IMPROVEMENT OF FACILITIES OF
  WATER DISTRICT NOS. 1 AND 2, AND AUTHORIZING THE ISSUANCE
  OF BONDS OF SAID TOWN IN THE PRINCIPAL AMOUNT OF $1 1,058,000
  TO FINANCE SAID APPROPRIATION

 The specific objects or purposes for which the bonds are authorized is the increase and
  improvement of
 facilities of the Districts in accordance with a lease agreement between the Erie County
  Water Authority
(“ECWA”) and the Town, consisting of improvements to (i) the Water Main Replaceme
  nt and Pump
 Station Improvements serving properties located within Water District No. 1, at the
  estimated maximum
cost of $9,738,000; and (ii) Water Main Replacement Improvements serving properties
  located within
Water District No. 2, at the estimated maximum cost of $1 ,320,000, as more
  particularly described in the
Map, Plan and Report for the Town of Boston Water System Improvements to
  Water Districts No. 1 and
2 dated August 2020 and updated October 2021 prepared by CPL Engineers.
The maximum amount of obligations authorized to be issued is $1 1,058,000

The period of probable usefulness is forty (40) years.

A complete copy of the bond resolution summarized above and the above-re
  ferenced map, plan and report
shall be available for public inspection during normal business hours at the
  office of the Town Clerk,
Town of Boston, 8500 Boston State Road, Boston, New York 14025