Read the whole document on one page (all 15 pages, each with its own heading)

WEST SENECA COURT ROOM  TOWN BOARD PROCEEDINGS
1250 Union Road  Minutes - Meeting # 2026-02
West Seneca, NY 14224  January 26, 2026

Town Engineer Foote provided the following updates:
- The town was denied the following grants and has requested as formal debrief from NYSDEC and
NYSEFC
  - 2025 WIIA Water grant for the replacement of water mains along Seneca Street and within
Water District No. 2
  - 2025 WIIA Sewer grant
  - 2025 WQIP grant for the proposed Phase 9 Sanitary Sewer Project
- Requested to modify the schedule for the NYSDEC Consent Order
- Requesting Town Board approval to submit grant applications for the following recommended
projects:
  - 2026 WIIA Water Grant – Consideration for replacement of the Orchard Park Road water main in
advance of the NYSDOT project which is expected to be completed in 2027-2028. The water mains
are listed on the ECWA recommended improvement list. Additionally, there should be consideration
to upsize the sanitary sewer mains. The work could be completed as part of the DOT project as a
betterment.
  - 2026 WQIP Sewer and 2026 WIIA Grant – Consideration for the replacement and upsize of the
sanitary sewer mains along Orchard Park Road or for Phase 10 Sanitary Sewer Project which builds
upon prior rehabilitation efforts and supports continued compliance with the Consent Order.

Councilmember Robertson asked where the connection is located. Mr. Foote stated near the medical
park on Orchard Park Road.

Councilmember Piekarec asked where the cost of Phase 8 currently stands and is Mr. Foote certain
there will be funds remaining when completed. Mr. Foote stated there is approximately $800,000 and
is hopeful a sag in the sewer line on West Willowdale and the pipe on Potters Road could be
addressed. Councilmember Piekarec asked if the NYSDEC has signed off on these projects. Mr.
Foote stated the two projects are maintenance. Councilmember Piekarec asked if property owners
are being approached regarding the access roads construction. Mr. Foote stated the property owners
will be contacted.

Councilmember Robertson asked how the sagging lines were identified. Mr. Foote stated the sagging
was discovered when the lines were televised and cleaned, the intention was to replace them in
Phase 9. Supervisor Dickson stated the Potters Road line had been known. Councilmember
Robertson asked when the grant applications are due and the funding they would provide. Mr. Foote
stated the applications are due in May and the funding would be 70% for WQIP, 25% for WIIA for
sewer, and 60% for WIIA for water. Councilmember Robertson asked Mr. Foote to provide costs for
the Town Board's review. Supervisor Dickson stated the town can apply for a Congressional Earmark
for Phase 9.

Councilmember Sherman asked for clarification of the SCADA software and the cost. Mr. Foote
explained that real-time sewer levels and flow rates are provided noting the town currently has a very
antiquated system. Mr. Foote stated the cost is approximately $100,000 and there could be some
cost offsets. Councilmember Piekarec stated this system would be helpful along Orchard Park Road.
3. PRESENTATIONS
1. Supervisor Dickson re Farmer Pirates composting program