will be fully restored by engineering methods and materials consistent with the specifications
  of the USDA Soil Conservation Service.

  All severed tile drain lines should be repaired, maintaining original gradient, using methods
  and materials consistent with the specifications of the USDA Soil Conservation Service. All
  repairs and protective sleeving should be shouldered firmly at least three feet beyond the limit
  of the water/sewer line excavation.

Future drainage

  During project planning and design, all operators of affected farmland should be inventoried
  for future locations of surface or subsurface drainage. All such locations should be noted in
  the design.

  Depth and gradient for such future surface or subsurface drainage installation, consistent with
  USDA Soil Conservation Service engineering specifications, should be accommodated by
  appropriate engineering of the depth-of-pipeline beyond the minimum burial of 4.0 feet as
  applicable.

Deep Ripping and Stone Removal

The dense compaction of the soil should be alleviated together with stone removal prior to the final
seedbed preparation.

Standard: During periods of relatively low to moderate soil moisture, the affected right-of-way
should be alternately deep chiseled and rock-picked until uplifted stone/rock materials of four
inches and larger size are cleared off the site and disposed of properly.

Revised: 10/16/02