REGULAR BOARD MEETING  TOWN HALL
MAY 6, 2026  7:30 P.M.
This resolution shall take effect immediately.

  Supervisor Keding  Yes  Councilwoman Martin  Yes
  Councilman Penders  Yes  Councilwoman Selby  Yes
  Councilman Stephan  Yes
five (5) Yes  Carried

A motion was made by Councilwoman Martin and was seconded by
Councilwoman Selby,
RESOLUTION 2026 - 41  ADOPTION OF LATERAL RESTRICTIONS –
  WATER/SEWER SERVICE WITHIN AGRICULTURAL DISTRICTS
WHEREAS, the Town of Boston is undertaking water system improvements within
ECWA Boston Water District No. 1 and may establish future water districts along
portions of Lango Road, Boston Colden Road (County Road 222), and Cole Road
(County Road 442); and
WHEREAS, portions of the project area are located within a county adopted, State
certified agricultural district; and
WHEREAS, the New York State Department of Agriculture and Markets requires the
imposition of lateral restrictions on water and sewer service within agricultural
districts in order to protect agricultural lands and limit non-farm development;
and
WHEREAS, the Town Board of the Town of Boston desires to adopt such lateral
restrictions consistent with State guidance and applicable law, including Public
Health Law §1115;
NOW, THEREFORE, BE IT RESOLVED, that the Town of Boston imposes the
following conditions, as warranted or recommended, on the management of
water/sewer lines located within ECWA Boston Water District No. 1 and future-
created Water Districts along portions Lango Road, Boston Colden Road (County
Road 222), and Cole Road (County Road 442) within an agricultural district:

(1)  The only land and/or structures which will be allowed to connect to the
  proposed waterline or sewer within an agricultural district will be existing
  structures at the time of construction, future agricultural structures, and
  land and structures that have already been approved for development by the
  local governing body prior to the filing of the Final Notice of Intent by the
  municipality.
  Land and structures that have been approved for development refer to those
  properties/structures that have been brought before a local governing body
  where approval (e.g., subdivision, site plan, and special permit) is needed to
  move forward with project plans, and the governing body has approved the
  action. If no local approval is required for the subdivision of land and/or
  the construction of structures, the municipality accepts the limitation under
  Public Health Law §1115 that defines a “subdivision,” in part, as “any tract
  of land which is divided into five or more parcels.” Water and/or sewer
  service will not be extended to the fifth and subsequent parcels where no
  local approval is required, and the land is located within a county adopted,
  State certified agricultural district.