Draft Colden Chapter #101 Battery Energy Storage Systems
  Planning Board Revision #15 (dated 8/10/26)

  The Decommissioning Plan shall address removal, transport, recycling, disposal, and
  lawful management of batteries, electrolytes, contaminated materials, and any associated
  hazardous substances.

 Section 101-10: Permit Time Frame and Abandonment

  A. The Building Permit associated with the Special Use Permit and site plan approval for a
  battery energy storage system shall be valid for a period of 24-months, provided that a building
  permit is issued for construction and construction is commenced. In the event construction is
  not completed in accordance with the final site plan and schedules, as may have been
  amended and approved, as required by the Colden Town Board, within 24-months after
  approval, the Town Board, at their discretion, may extend the time to complete construction for
  up to 180-days. If the owner and/or operator fails to perform substantial construction after 36-
  months, the approvals shall expire.
  B. The battery energy storage system shall be considered abandoned when it is no longer capable
  of the storage and delivery of energy to the grid for a period of 12 consecutive months. If the
  owner and/or operator fails to comply with decommissioning upon any abandonment, the Town of
  Colden may, at its discretion, enter the property and utilize the available bond and/or security
  for the removal of a Tier 2 Battery Energy Storage System and the full restoration of the site in
  accordance with the decommissioning plan.
  C. Conditions in a Colden BESS Special Use Permit shall include a provision which requires an
  annual inspection by Town of Colden Officials during the Annual Scheduled SUP Inspection
  Day. Advance notification of the inspection will be provided by the Town Clerk’s Office via
  notice addressed to the designated official for the Tier 2 BESS Site.

  ARTICLE III
  FEES

Section 101-11. Fees

For a Tier 1 BESS, a non-refundable Town of Colden “Battery Energy Storage System (BESS) Permit”
application fee, and a Building Permit Fee shall be due for Tier 1 Battery Energy Storage System
developments. The fees shall be as determined by the Town of Colden’s fee and fines schedule, as
updated from time to time by the Town Board, with all fees paid by the Applicant. The Code Enforcement
Department and/or the Town Clerk’s office should be consulted by the Applicant to inspect the current
Fines and Fees schedule adopted by the Town Board.

For a Tier 2 BESS, a non-refundable application fee, a non-refundable Special Use Permit Fee, an
annual Special Use Permit Inspection fee, and a Building Permit Fee shall be due for Battery Energy
Storage System developments. The fees shall be as determined by the Town of Colden’s fee schedule,
as updated from time to time by the Town Board, with all fees paid by the Applicant. The Code
Enforcement Department and/or the Town Clerk’s office should be consulted by the Applicant to inspect
the current Fines and Fees schedule adopted by the Town Board. Due to the complexity and the
specialty skills involved in a Tier 2 BESS, it is presumed that the Town will employ certain professional
services during review of the applicant’s Special Use Permit and Building Permit submissions. Since
those Professional Engineering and Specialized Consultant activities cannot well defined in advance, the
recovery of costs for those services will be in accordance with the Time and Materials municipal billing
rates of the engaged professional. In addition to engineering and specialized consultants the Town shall
also be reimbursed for legal review and analysis associated with the BESS application; such reviews

 TOWN OF COLDEN – BATTERY ENERGY STORAGE SYSTEMS  16