Draft Colden Chapter #101 Battery Energy Storage Systems
  Planning Board Revision #15 (dated 8/10/26)

  (z) Panelboards
  (aa) HVAC/thermal management system
  (bb) Fire rated material
  (cc) Storage batteries and battery storage systems shall comply with the following:
  (dd) Storage batteries shall be listed in accordance with UL 1973
  (ee) Prepackaged and pre-engineered battery energy storage systems shall be
  listed in accordance with UL 9540. Exception: Lead-acid batteries are not
  required to be listed
  (ff) An approved energy management system shall be provided for battery
  technologies other than lead-acid and nickel cadmium for monitoring and
  balancing cell voltages, currents, and temperatures within the manufacturer’s
  specifications. The system shall transmit an alarm signal to an approved
  location if potentially hazardous temperatures or other conditions such as
  short circuits, over voltage or under voltage are detected.
  (8) Structural Requirement Compliance:
  (a) If the battery energy storage system is wall mounted and its weight is more
  than 200 pounds, provide structural details in the drawings and calculations as
  a separate document (Uniform Code).
  (b) If multiple battery energy storage systems are installed and the combined
  weight is 400 pounds or more, provide structural details in the drawings and
  calculations as a separate document (Uniform Code).
  B. Utility Lines and Electrical Circuitry. All on-site utility lines shall be placed underground to the
  extent feasible and as permitted by the serving utility, especially in the case of residential or
  commercial sites which require new or upgraded infrastructure from the serving utility.
  Exceptions are allowed for the main disconnect, if any, at the utility company right-of-way and
  any new interconnection equipment, including without limitation any poles, with new
  easements and right-of-way.
  C. Signage. No permanent BESS signage at the road or in or near the roadway right of way is
  permitted, with the exception of temporary promotional advertisement for the project
  contractor during, or immediately following the site’s commissioning. The presence of any
  promotional sign is limited to 60 days after approval and closeout of the Town of Colden
  permits.

Section 101-8: Permitting Requirements for Tier 2 Battery Energy Storage Systems (> 600kWh)

Tier 2 Battery Energy Storage Systems are permitted only through the issuance of a Special
Use Permit and may only be considered within the Agricultural (Ag) zoning district. Tier 2
BESS projects are larger, potentially Utility-Scale Systems, and shall be subject to the Uniform
Code and the rigorous site plan review and application requirements set forth in this Section.
Tier 2 applications via Special Use Permits, must be in full compliance with all submission
requirements before they shall be considered a “complete application” by the reviewing
agencies in Colden.

  A. Applications for the installation of Tier 2 Battery Energy Storage System shall be:
  (1) Reviewed by the Code Enforcement Department, the Colden Planning Board, and the
  Colden Environmental Board for completeness. An application shall be deemed
  complete when it addresses all matters listed in this Local Law including, but not
  necessarily limited to,

TOWN OF COLDEN – BATTERY ENERGY STORAGE SYSTEMS  7