TO: Honorable Town Board FROM: Jason Foote, Town Engineer DATE: February 9, 2026 SUBJECT: Town Engineer re Water District 8 Water System Improvements Close Out Change Order Requested Action: Please authorize the supervisor to execute the attached final Change Order 1 for the Water District 8 Water Systems Improvements Project. The change order is a deduct of $184,746.05. We have received the necessary paperwork from E & R General Construction, Inc. to close out the project. Feel free to contact me if you have any questions. RESOLUTION: ATTACHMENTS: 1. Change Order 1 for Water District 8 Waterline Project Page 34 of 177