Town of West Seneca - Capital Project Management (2019M-195) (full text)
Page 1
DIVISION OF LOCAL GOVERNMENT AND SCHOOL ACCOUNTABILITY
REPORT OF EXAMINATION | 2019M-195
Town of West Seneca
Capital Project Management
MARCH 2020
Page 2
Contents
Report Highlights . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Capital Project Management . . . . . . . . . . . . . . . . . . . . . . . 2
How Should a Board Plan, Authorize and Monitor a Capital Project?. . 2
The Board Was Not Fully Transparent About the Project Scope
and Budget. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
What Do We Recommend? . . . . . . . . . . . . . . . . . . . . . . . 7
Appendix A – Response From Town Officials . . . . . . . . . . . . . . 8
Appendix B – Audit Methodology and Standards . . . . . . . . . . . 10
Appendix C – Resources and Services. . . . . . . . . . . . . . . . . 11
Page 3
Report Highlights
Town of West Seneca
Audit Objective
Background
Determine whether the Town properly planned and
managed a capital project. The Town of West Seneca
(Town) is located in Erie County.
Key Findings The Town is governed by an
elected Town Board (Board)
The Board: composed of a Supervisor and
four Board members. The Board
ll Did not properly plan and manage the capital project
is responsible for the general
and clearly inform taxpayers when the estimated cost
management and oversight of the
and scope of the project changed.
Town’s financial operations. The
ll Was not fully transparent on the anticipated project Supervisor serves as the chief
costs. As a result, original estimates were $9.8 fiscal officer.
million and increased by more than $3.6 million after
competitive bids were received. In September 2016, the Board
accepted an engineering and
Town officials did not: architectural proposal for library
ll Ensure an itemized project budget outlining revenues
renovation and construction of
and expenditures was maintained in the accounting a community center and Town
records and periodically updated. offices. The project was completed
in June 2018.
Key Recommendations Quick Facts
ll Prepare realistic estimates and ensure the project
Population 44,700
costs are clearly defined.
Initial Estimated Project
ll Prepare and approve an itemized budget, and amend $9.8 million
Cost
and update the budget as the project changes.
Final Project Cost $13.5 million
Town officials agreed with our recommendations and
indicated they planned to take corrective action. Debt Issued $10.3 million
Audit Period
January 1, 2012 – July 31, 2019
Of f ic e of t he New York State Comptroller 1
Page 4
Capital Project Management
How Should a Board Plan, Authorize and Monitor a Capital Project?
A governing board is responsible for the oversight and management of capital
projects, including ensuring that projects are properly planned and managed,
funding is authorized and costs are kept within the approved budget. The
board and town officials should monitor progress and implement necessary
changes to ensure the project is completed in the most cost-effective manner.1
Proper planning of a capital project requires that the board have a thorough
understanding of the project’s overall scope and estimated cost before authorizing
the project. Initial estimated costs must be realistic so a board can plan financing
and keep the taxpayers informed.
When financing a project with debt, a board must adopt a bond resolution at
the project’s inception that includes, among other things, a statement of specific
objects or purposes or class of objects or purposes for which the obligations to
be authorized by the resolution are to be issued and a statement of the estimated
maximum cost and a plan of financing of the total cost. In lieu of this statement,
the resolution may specify that such information has been set forth in a capital
budget or in an appropriation for such specific or class of objects or purposes
or in a previously adopted bond resolution. After adoption of a capital budget,
the supervisor is responsible for properly recording the project budget and
subsequent financial activities.
The board should ensure that any changes to the project plan are within the
project scope or premise of the initial proposal and update the corresponding
budget. The board should ensure that all its actions and proceedings are
documented in official records to ensure transparency to taxpayers. The board
should monitor the status of the project by reviewing monthly financial reports that
compare actual revenues and expenditures to the related budget.
The Board Was Not Fully Transparent About the Project Scope and
Budget
The Board began planning a repair and maintenance project for the library in
2012, which expanded to a plan to construct a community center. According to
the September 24, 2012 Board minutes, the Board requested the Town engineer2
to prepare architectural drawings and plans for the library as part of the overall
concept plans for the site.
In July 2014, the Board and engineer presented a plan to renovate the existing
library and include a 10,000 square foot addition. The Board minutes indicated
1 Refer to our publication Capital Projects Fund available at www.osc.state.ny.us/localgov/pubs/lgmg/capital-
projects-fund.pdf
2 The Town hired an outside engineer to serve as Town engineer.
2 Of f ic e of t he New York State Comptroller
Page 5
that the existing library (7,000 square feet) would be renovated at a cost of $175
per square foot and the addition would be constructed at a cost of $275 per
square foot, which we calculated at an estimated total cost of $3.9 million.
The Supervisor told us that in November 2014 a snow storm damaged the
building that housed the Town’s recreation department and in 2015, another
building, which housed the Town’s finance office, was found to have damage.
Due to concerns, the finance office was moved to a temporary location. The
Supervisor told us that it became necessary to address these issues by including
them in the capital project. Additionally, the Board wanted to create a community
center that Board members believed would be a catalyst for the Town’s economic
development and growth.
The engineer prepared a preliminary estimate of $9.8 million for the community
center construction and library renovation project, which was presented to the
Board in March 2016. This estimate included such things as unfinished space for
future offices on the first floor, a community recreation room, first floor mechanical
room and unfinished space for a café. Based on this estimate, on May 23, 2016,
the Board passed a bond resolution subject to permissive referendum3 that
determined the estimated maximum cost of the project to be $9.8 million.
The project was to be financed by the issuance of up to $8.4 million in serial
bonds, application of $1.4 million in funding from the Town’s equipment lease/
purchase agreement dated February 12, 2016, related to the Town’s energy
performance contract dated November 15, 2014 (energy performance contract
funding), and application of any funding expected to be received from the
State for the project. The $9.8 million estimated maximum cost included $7.9
million for building repairs and construction and $1.9 million for furnishings and
contingencies. In September 2016, the Board formally accepted the proposal from
the engineer’s firm to provide engineering and architectural services related to
the project; this proposal stated that the project budget was approximately $9.5
million.
The Board solicited bids in October 2016, which were received in November, and
awarded to five contractors on December 5, 2016. While the engineer’s initial
estimate for the project was $9.8 million, the post-bid estimated cost increased
to more than $13.4 million, approximately $3.6 million more than the estimated
maximum cost established by the Board. According to a memo from the engineer
to the Board dated December 5, 2016, the bids were more than the initial
estimate because it was made prior to the addition of second-story office space
3 A permissive referendum is a ballot proposition submitted to qualified electors of the town at a special
election, to approve or disapprove a bond resolution that has been adopted by the town board. A permissive
referendum is held if the requisite number of qualified electors petitions the town board to hold the special
election for the ballot proposition.
Of f ic e of t he New York State Comptroller 3
Page 6
and the high ceiling space for the recreation department. The memo stated that
the additional work would require an additional borrowing of $2.2 million.
The Supervisor told us this change allowed for the mechanical room to be
moved to the second floor, the addition of unfinished space for future offices on
the second floor and an increase in ceiling height for the recreation department
to allow for a half-court for basketball. However, Town officials were unable to
provide us with documentation showing, nor could we find evidence in the Board
minutes, that the Board adopted another resolution to effect these changes and
increase the estimated cost of the project before soliciting bids or starting the
project. However, the October 31, 2016 architectural plans provided to us by
the engineer included the additional work and these plans were included in the
contract documents provided for contractors to inspect when preparing their bids.
Figure 1: Comparison of the Board’s Maximum Cost Estimates with Post-Bid
Estimates
Board Approved Post-Bid
Project Element Maximum Cost Estimate Difference
Estimate (May 2016) (January 2017)
Repairs and Construction $7,865,045 $11,895,100 $4,030,055
Furnishings and Contingency $1,967,000 $1,551,030 ($415,970)
Total Costs $9,832,045 $13,446,130 $3,614,085
Although the initial plan included some first floor unfinished office space,4 we
question whether $3.6 million (37 percent) in additional costs over the original
estimate was within the overall scope of the original project plan established
by the Board and presented to the public. Town officials and the engineer were
unable to provide us with an amended budget reflecting the added costs due to
these changes.
The increase in cost, and the change in plan were documented in the Board
minutes only after the bids were received. Additionally, we found no evidence
that the engineer’s memo explaining the increase in cost was made available to
taxpayers, because it was not documented in the Board’s record of proceedings.
In addition, the post-bid project estimates and subsequently updated budget
were not prepared in the same itemized format as the original estimate. For
example, the original estimate itemized the different elements of the building,
thereafter updated estimates were presented based on total bid amounts for each
contractor’s trade.5
4 First floor cubicles and a mechanical room.
5 General, mechanical, electrical, plumbing and fire protection contractors.
4 Of f ic e of t he New York State Comptroller
Page 7
After construction began, on January 18, 2018, the Board adopted a bond
resolution, subject to permissive referendum,6 authorizing additional financing
for the project with a revised estimated maximum cost of $14.9 million, or $5.1
million more than the initial cost estimate. The plan of financing included the
issuance of up to $5.1 million in serial bonds, in addition to the $8.4 million in
bonds previously authorized by the May 23, 2016 bond resolution, application of
$1.4 million in energy performance contract funding and application of $1.6 million
in grant funds expected from the State. Total financing sources included in this
resolution totaled $16.5 million (more than the project’s estimated maximum cost
indicated in the resolution by approximately $1.6 million). Officials did not prepare
a detailed itemized budget in connection with this bond resolution to demonstrate
the reason for the increase in the estimated cost.
While the Board established financing sources needed to fund the project,
only the initial revenue and appropriation budget entries were recorded in the
accounting system. Subsequent budget changes were not recorded in the
system. As a result, up-to-date budget status reports could not be prepared.
Consequently, the Board was unable to effectively monitor the project by ensuring
financing sources were sufficient to fund expenditures or that the budget was
always in balance. After appointment in September 2017, the Director of Finance
manually prepared spreadsheets that were used by the Board and Town officials
to monitor the project.
Following the adoption of the January 18, 2018 bond resolution, in February 2018,
the Board was petitioned by residents seeking a referendum on that resolution. In
light of the petition, the Board passed a resolution on February 26, 2018 stopping
any further project expenditures, and directing the Town Attorney, the Director of
Finance and the Town’s engineering firm to work with outside counsel, outside
accountants and project contractors to provide a report and recommendations
concerning the project, including the status of construction, costs incurred, legal
obligations and available savings from changes in the scope of work, among
other things.
Before the referendum could be held, the Board adopted a resolution on March
12, 2018 to rescind the January 18, 2018 bond resolution. As a result, residents
were unable to vote on that particular borrowing authorization. At the March 12,
2018 meeting, the Board adopted another bond resolution, subject to permissive
referendum, with an estimated maximum project cost to be approximately $13.4
million.
The revised financing plan included the issuance of up to $1.9 million in serial
bonds in addition to the $8.4 million bonds previously authorized by the May 23,
2016 resolution, application of $1.4 million in energy performance contract funding
6 This resolution was subsequently rescinded, as discussed below.
Of f ic e of t he New York State Comptroller 5
Page 8
and $1.6 million in grant funds expected to be received from the State. The March
12, 2018 bond resolution included an estimated maximum cost for the project
that was $1.5 million less than the January 18, 2018 bond resolution’s estimated
maximum cost of $14.9 million.
The Board minutes for the March 2018 meeting included the reports received
from Town officials requested by the previously discussed February 26, 2018
resolution. The report from the Town Attorney stated that the original bond
resolution was adopted before the final design and the project was publicly bid.
The report also indicated that $3.1 million of the $5.1 million proposed serial bond
funding on January 18, 2018 was to serve as money to be used to address cash
flow issues while waiting for grant reimbursement, and not the actual cost of the
project. If the Board intended to use $3.1 million for cash flow purposes, it was not
transparent to taxpayers because the increase in estimated cost to $14.9 million
made it appear to be necessary to complete the project.
Figure 2: Project Estimates vs. Final Cost
FIGURE 2
Project Estimates vs. Final Cost
$14.9 million
$13.4 million $13.4 million $13.5 million
$9.8 million
March 2016 January 2017 Post- January 2018 March 2018 Final Cost
Estimate Bid Estimate Estimate Estimate
The Town Attorney’s report also stated that the $3.1 million intended for cash flow
purposes was no longer needed because certain grants had been received, which
the Town’s consultants were unaware of. Therefore, the estimate of required cash
was overstated. We found that as of March 12, 2018, the energy performance
contract funding and one grant totaling $1.9 million were received and/or available
as of February 2016.
Further, the Town Attorney’s report specified that the $14.9 million in estimated
cost was overstated by $1.4 million as costs related to the energy performance
contract funding was included twice after a miscommunication between the
engineer and bond counsel. The Supervisor and the engineer were jointly
responsible for preparing reports used by the Board to monitor the project and
6 Of f ic e of t he New York State Comptroller
Page 9
it appears that they had adequate time to communicate accurate information to
the engineer and bond counsel. Additionally, if detailed itemized reports were
prepared, Town officials may have been able to identify and correct such reporting
errors. The other two grants totaling approximately $594,000 were received
on April 30, 2018, and two grants, totaling approximately $592,000, were still
outstanding at the end of our audit fieldwork.
When inaccurate costs are included in project estimates, there is an increased
risk that the Board may issue more debt than necessary. In addition, there is risk
the additional funding may be used for costs that were not in the original project
scope.
The Board and Town officials did not properly plan and manage the capital
project and clearly inform taxpayers when the estimated cost and scope of the
project changed. Had the Board provided more detailed and accurate budgetary
information and better explained how the financing sources would be used,
taxpayers would have been in a better position to make more informed decisions.
What Do We Recommend?
The Board should:
1. Prepare and approve an itemized budget and amend and update it as the
project plan changes.
2. Ensure all Board action and proceedings are recorded in the official Board
minutes to ensure transparency to taxpayers.
3. Ensure accurate cost estimate schedules or budgets are available in
connection with the bond resolution.
The Supervisor should:
4. Ensure complete and accurate accounting records are maintained and
provide the Board with monthly reports comparing actual revenues and
expenditures to budgeted amounts.
Of f ic e of t he New York State Comptroller 7
Page 10
Appendix A: Response From Town Officials
8 Of f ic e of t he New York State Comptroller
Page 11
Of f ic e of t he New York State Comptroller 9
Page 12
Appendix B: Audit Methodology and Standards
We conducted this audit pursuant to Article V, Section 1 of the State Constitution
and the State Comptroller’s authority as set forth in Article 3 of the New York
State General Municipal Law. To achieve the audit objective and obtain valid audit
evidence, our audit procedures included the following:
ll We interviewed Town officials and reviewed Board minutes to determine
whether the Board adopted a resolution that established and identified the
project, authorized the maximum estimated cost and established how the
project would be financed, and to determine whether the Board and Town
officials prepared an itemized budget.
ll We reviewed the available project budget to ensure the Board and Town
officials prepared a balanced budget and that the Town had adequate
financing sources to cover the estimated cost of the project.
ll We reviewed Board minutes to assess whether the Board properly
established and documented bond resolutions.
ll We assessed the adequacy of the monthly financial reports the Supervisor
and/or Town officials provided to the Board to monitor the project.
We conducted this performance audit in accordance with GAGAS (generally
accepted government auditing standards). Those standards require that we
plan and perform the audit to obtain sufficient, appropriate evidence to provide a
reasonable basis for our findings and conclusions based on our audit objective.
We believe that the evidence obtained provides a reasonable basis for our
findings and conclusions based on our audit objective.
The Board has the responsibility to initiate corrective action. A written corrective
action plan (CAP) that addresses the findings and recommendations in this report
should be prepared and provided to our office within 90 days, pursuant to Section
35 of General Municipal Law. For more information on preparing and filing your
CAP, please refer to our brochure, Responding to an OSC Audit Report, which
you received with the draft audit report. We encourage the Board to make the
CAP available for public review in the Town Clerk’s office.
10 Of f ic e of t he New York State Comptroller
Page 13
Appendix C: Resources and Services
Regional Office Directory
www.osc.state.ny.us/localgov/regional_directory.pdf
Cost-Saving Ideas – Resources, advice and assistance on cost-saving ideas
www.osc.state.ny.us/localgov/costsavings/index.htm
Fiscal Stress Monitoring – Resources for local government officials
experiencing fiscal problems
www.osc.state.ny.us/localgov/fiscalmonitoring/index.htm
Local Government Management Guides – Series of publications that include
technical information and suggested practices for local government management
www.osc.state.ny.us/localgov/pubs/listacctg.htm#lgmg
Planning and Budgeting Guides – Resources for developing multiyear financial,
capital, strategic and other plans
www.osc.state.ny.us/localgov/planbudget/index.htm
Protecting Sensitive Data and Other Local Government Assets – A non-
technical cybersecurity guide for local government leaders
www.osc.state.ny.us/localgov/pubs/cyber-security-guide.pdf
Required Reporting – Information and resources for reports and forms that are
filed with the Office of the State Comptroller
www.osc.state.ny.us/localgov/finreporting/index.htm
Research Reports/Publications – Reports on major policy issues facing local
governments and State policy-makers
www.osc.state.ny.us/localgov/researchpubs/index.htm
Training – Resources for local government officials on in-person and online
training opportunities on a wide range of topics
www.osc.state.ny.us/localgov/academy/index.htm
Of f ic e of t he New York State Comptroller 11
Page 14
Contact
Office of the New York State Comptroller
Division of Local Government and School Accountability
110 State Street, 12th Floor, Albany, New York 12236
Tel: (518) 474-4037 • Fax: (518) 486-6479 • Email: [email protected]
www.osc.state.ny.us/localgov/index.htm
Local Government and School Accountability Help Line: (866) 321-8503
BUFFALO REGIONAL OFFICE – Jeffrey D. Mazula, Chief Examiner
295 Main Street, Suite 1032 • Buffalo, New York 14203-2510
Tel (716) 847-3647 • Fax (716) 847-3643 • Email: [email protected]
Serving: Allegany, Cattaraugus, Chautauqua, Erie, Genesee, Niagara, Orleans, Wyoming
counties
Like us on Facebook at facebook.com/nyscomptroller
Follow us on Twitter @nyscomptroller