§ 200-56.3. Basements.13 [Added 8-14-2007 by L.L. No. 4-2007]

All single or multiple dwellings shall have a full basement or a minimum four-foot crawl space, both
in regard to height and area, constructed in accordance with the standards of Chapter 84, Building
Construction.

§ 200-56.4. Portable temporary storage units. [Added 3-12-2019 by L.L. No. 1-2019; amended
5-14-2019 by L.L. No. 3-2019]  Commented [NZ13]: What issues are we having with
  storage?
A.  Portable temporary storage units, also known as PODs, SAMs, etc., are defined as a portable
  Commented [NB14R13]: I know the want to “tighten up
  (temporary) transportable container, trailer, storage unit, shed-like container or other portable  process” but we sort of skimmed over what the actual
  structure, used for the temporary storage of building materials, household items, personal property or  problem is. Any insight from expereinces with the Town
  other materials, for a limited time.  would be appreciated!
  Commented [RK15R13]: The “temporary” nature of the
B.  Intended use is for temporary storage of building materials, household goods, personal items or other  PODS has become permanent. There is no teeth to enforce
  materials off-site.  them to remove them.

C.  The duration of use is limited in accordance with the following:

  (1)  Temporary storage units may be placed on or at a property in the Town, without fee, for a time
  period of 30 calendar days. At the end of the thirty-day period, the unit must be removed from
  the premises within a ten-day grace period. The time period begins on the date of delivery of the
  unit to the property site. In the event the applicant wishes to extend the time period that is
  granted initially, under this section, an extension may be issued by permit by the Code
  Enforcement Officer if requested, and upon payment to the Town of Wales of a permit extension
  fee as listed in the Fee Schedule, as set forth by resolution of the Town Board. Extension
  requests must be made prior to the expiration of the ten-day grace period. In no case shall a
  temporary storage unit be placed on or at a property for more than 60 consecutive days or more
  than 60 days in a calendar year unless special circumstances arise as listed in Subsection C.
  (2)  The following circumstances shall grant an applicant a permit for the placement of a temporary
  storage unit on or at a property for a period of time which exceeds the period set in Subsection
  C(1) above:
  (a)  In the event of fire or other natural disaster which causes substantial damage to the primary
  structure of the property, a temporary storage unit may be placed on or at the property for
  a period of time while repairs are made and as determined necessary by the C.E.O. Once
  repairs have been made, the temporary storage unit shall be removed from the property
  within 10 days. In the event the applicant wishes to extend the time granted past that
  allowed under these circumstances, a new application for a permit pursuant to Subsection
  C(1) must be submitted. In this instance, applicable fee(s) may be waived by the C.E.O.
  (b)  The renovation, expansion or other alteration to an existing permanent structure may
  require the removal of personal property from the structure and/or storage of said personal
  property outside of the structure. The period of time the temporary storage unit may be
  located on or at said property shall be determined by the C.E.O., based on the type of work
  being performed and/or 10 days after the building permit issued for the required work
  expires.
  (c)  Applicant must obtain a temporary storage unit permit prior to obtaining and placing a unit
  on or at a property in the Town, without fee, for a time period of 30 calendar days. At the
  end of the thirty-day period, the unit must be removed from the premises within a ten-day

  34