Town of Aurora | Town Board Meeting | July 27, 2026
  e) Combined attendance at simultaneous events shall not exceed 100 persons,
  inclusive of employees and/or contractors

  f)  All events to be private with only invitees attending, meaning events are not
  open to the general public; and

WHEREAS, as an unlisted action under SEQR the Town Board found that the project will
not result in any significant adverse environmental impacts.

NOW, THEREFORE, BE IT

RESOLVED, that pursuant to Town Code §95-2B(2) of the Town of Aurora, the Town Board
of the Town of Aurora does hereby grant the attached Special Use Permit, including
aforementioned conditions, to Rachel Krajewski/Carner Development Group, to
operate a campground and construct seasonal cottages, treehouses, a lodge, and
convert the existing residences into sleeping rooms and an administration building at
1196 Big Tree Road, East Aurora, NY.

[Deputy Supervisor McCann brought up a discussion about occupancy. The Board
discussed limiting attendance at the proposed campground and event venue.
Councilmember Armbrust recommended reducing the event limit from 100 attendees to
80 because the lodge’s building-code occupancy is 80 and the site has only 30 parking
spaces.

Code Enforcement Officer Cassidy explained that the 80-person limit applies only inside
the lodge, while other guests could be elsewhere on the property. The Board agreed
instead to cap the total number of people attending all concurrent events at 100,
including employees and contractors.

The Board also agreed that a caretaker or responsible person must be present whenever
the campground is operating. The SUP Resolution and Site Plan Resolutions reflect these
changes.]

Upon a vote being taken: ayes – four; noes – none; recusal – one by Councilmember  Action #255
Garvey. Motion carried.  1196 Big Tree Rd
  Site Plan approved
  Councilmember Armbrust moved to adopt the following resolution, seconded
by Councilmember Wrazen:

  RESOLUTION APPROVING SITE PLAN
  1196 Big Tree Road (SBL#165.00-1-28.21)

WHEREAS, Rachel Krajewski/Carner Development Group has submitted a Site Plan
Review Application to operate a campground and construct seasonal cottages,
treehouses, a lodge, and convert the existing residences into sleeping rooms and an
administration building for SBL#165.00-1-28.21 at 1196 Big Tree Road, East Aurora NY; and

WHEREAS, at their May 6, 2026 meeting the Aurora Town Planning Board recommended
approval of the site plan; and

WHEREAS, Town Board of the Town of Aurora stipulates that the applicant is required to
adhere to these conditions:

  a) Pursuant to Town of Aurora Zoning Code § 116-27(A)(11), the Town Board
  hereby finds that 30 parking spaces is sufficient, however if in the future with
  good cause shown after an opportunity for the Applicant and/or its successors
  and/or assigns to be heard, the Town Board may require up to 21 additional
  parking spaces to be constructed

  b) No outdoor wood fires of any kind are permitted. Propane or similar fire pits are
  permitted

  c) No outdoor amplified music or similar volume of manmade sounds from 10 PM
  to 8 AM

  d) A caretaker and/or responsible person must be present at all times when
  campground is in operation

  e) Combined attendance at simultaneous events shall not exceed 100 persons,
  inclusive of employees and/or contractors

  f)  All events to be private with only invitees attending, meaning events are not
  open to the general public; and

WHEREAS, the Site Plan application and documents were sent to Erie County
Department of Environment and Planning for review and issued a no recommendation,
determining it to be of local concern; and

WHEREAS, the Site Plan application and documents were sent to New York State
Department of Transportation (NYSDOT) in which they responded that a Traffic Impact
Study is required and pending and that in addition, a NYSDOT Work Permit will be
required for any work located in the State Highway; and