CARMINA WOOD DESIGN  Project No.:  25-4181  Date:  2/11/2026
  80 SILO CITY ROW, SUITE 100  Project Name:  Proposed Bank
  BUFFALO, NEW YORK, 14203  Project Address: 1465 Union Road - Town of West Seneca
  (716) 842-3165  Subject:  Sanitary Sewage & Domestic Water Demand Calcs
  FAX (716) 842-0263  Sheet:  1  of  1

Sanitary Sewage Demand Calculations:

  8  employees  @  15.0 gpd/employee  =  120 gpd

  Total Demand  =  120 gpd

Water Demand Calculations (Domestic):

  Contractor Shops:

  120 gpd  x  1.1  =  132 gpd  *use 110% of sewage demand

  *use 1.8 peaking factor and assume an 12 hour day

  132  gpd  x  1day/12hr  x  1hr/60min  =  0.18 gpm

  0.18 gpm  x  1.8  =  0.33 gpm  Qpeak
  Headlosses:
  Qpeak  =  0.33 gpm
  Pipe  =  1.00 inch  Type "k" copper  C  = 140
  Length =  61 LF (approx. distance from tap to RPZ)
  10.44 L Q1.85  10.44(61)(1.98)1.85
  HL =  =  =  0.01 ft  =  0.00 psi
  C1.85 D4.866  (140)1.85 (1)4.866
  Δ elev  =  8.5 ft  =  3.68 psi  *RPZ is located inside building
  Loss through meter  =  1 psi
  Loss through RPZ  =  12 psi
  Total Losses =  16.7 psi
  Static Pressure  =  80 psi  *from hydrant flow test
  Residual Pressure Following RPZ  =  80 - 16.7  =  63.3 psi  (available after rpz & meter)