ESTIMATE
Number: AAAQ13321-01  PARKITECTS, Inc.
Date:  Mar 10, 2026  279 Lakefront Blvd.
Project: Westgate Park CP Option 2 Full  Buffalo, NY 14202
  Install
  Sold To  Your Sales Rep  Terms
Town of West Seneca  Lucas Pruch  THIS IS AN ESTIMATE ONLY. A
Brian Adams  FINAL PROPOSAL WILL BE
  P  585-808-3436  ext:
1250 Union Road  CREATED TO PLACE THE ORDER.
  E  [email protected]
West Seneca, NY 14224
P  716-674-4850  ext:
F
E  badam [email protected]

 Qty  Item #  Description  Unit Price  Ext. Price
  LSI Play Equipment under Sourcewell Contract 101625-LSI
  1  PKG25-18  Park & Playground Package, PlayShaper Structure (2-5 Years)  $21,528.00  $21,528.00
  1  PKG25-22  Park & Playground Package, PlayBooster Structure (5-12 Years)  $71,013.00  $71,013.00
  1  PKG25-12  Park & Playground Package, Independents to Include: Cozy Dome,  $15,311.00  $15,311.00
  Double Bobble Rider, and Single Post Swings, 8' Beam with Toddler Swing
  Add-On Beam, Seats: (3) Belts, MBS (5-12 Years), and Full Bucket
  1  PKG25-12  Park & Playground Package, Site Furnishings to Include: (3) 72"  $3,219.00  $3,219.00
  TenderTuff Bench w/ Back and (1) 92" TenderTuff Bench w/o Back
  Subtotal  $111,071.00
  8.0% Contract Discount  - $8,885.68
  1  Freight  $6,500.00  $6,500.00
  Play Equipment Total  $108,685.32

  Safety Surfacing under Sourcewell Contract 101625-LSI
4,115  SF  Engineered Wood Fiber, 230 CY, delivered for 12" System  $2.25  $9,258.75
  7  Roll  Duraliner Fabric - 1,500 SF Roll  $275.00  $1,925.00
  62  EA  4' Timbers w/ Stake  $31.00  $1,922.00
  1  EA  Timber Access Wedge  $515.00  $515.00
  2  EA  Wear Mat Swing Bay & Oodle  $250.00  $500.00
  3  EA  Wear Mat Slide  $160.00  $480.00
  1  EA  Wear Mat Freight  $1,400.00  $1,400.00
  Surfacing Total  $16,000.75

  Installation Services under Sourcewell Contract 101625-LSI
  1  SF  Demo and Disposal of Existing Play Equipment  $12,500.00  $12,500.00
4,115 SF  Excavation and Site Prep  $5.00  $20,575.00
  1  Installation of Equipment by LSI Certified Installer  $44,500.00  $44,500.00
4,115 SF  Installation of Wood Fiber Surfacing System w/ (2) Layers Fabric, 3" Drain  $4.00  $16,460.00
  Stone, Wear Mats & ADA Access Ramps
 360  SF  Asphalt Walkway  $25.00  $9,000.00
  1  Restoration of Site  $6,000.00  $6,000.00
  1  Playground Code Compliance Audit (by third party)  $1,100.00  $1,100.00
  Installation Total  $110,135.00