Southtowns Record

2/10/26 Board Packet

Government
Village of Gowanda
Board
Village Board
Meeting
Feb 10, 2026
Kind
Agenda packet
Topics
Water, sewer and drainage, Public safety, Budget and taxes, Parks and recreation, Zoning and land use, Audits and oversight, Housing, Roads and traffic

Original document

Same meeting

Text · page 32 of 67

Read the whole document on one page (all 67 pages, each with its own heading)

This document was a scan. Its text was produced by character recognition and may contain errors; check the original for exact wording.

«  Interior and exterior building renovations for commercial and mixed-use spaces, e.g.
  fagade/storefront renovations, permanently affixed signage and awnings, commercial interior
  fit-out, HVAC, MEP, and other permanent building i improvements
  © Upper-story residential improvements
  e , Permanent commercial machinery and equipment, that is integral to the business and not a
  replacement of existing equipment unless it allows for rmore/new products to be offered and
  has a useful life of more than one year. and an acquisition cost of $2,000 or more per unit
  ¢  Soft costs — architectural, engineering, environmental
  ©  Public art

 1.c.3  Ineligible Activities
  e  Ineligible uses of funds include: acquisition costs; improvements to structures owned by
  religious or private membership-based organizations, improvements to municipally owned
  and municipally operated buildings; furnishings, appliances, electronics, tools, disposable
  supplies, incidental business equipment, non-permanentfixtures, temporary artwork.
  e - Funds may not be used for site work or ancillary activities on a property including but not
  limited to: septic systems/laterals, grading, parking lots, sidewalks, garages, sheds,
  landscaping, fences, general maintenance or repairs.
  e ~ Ineligible business activities include: inventory, rent or lease expenses, working capital or
  other undefined expenses that do not sustain business operations.
  ¢  Funds cannot be used for participant, participant’s family or participant’s staff labor. In-kind
  labor and the reimbursement for materials only is also not eligible.

1.c.4  Available Funding
  *  Building Renovation
  " The LPA may award between $25,000 - $15000 in Program funds, per building, not
  to exceed 75% of the total eligible project cost. Building renovation funds may be
  used to renovate facades, storefronts and commercial interiors, with an additional
  $25,000 per residential unit up to a per building maximurn of $200,000, not to exceed
  75% of the total project cost.
  ©  Minor Projects
  « The LPA may award between $10,000- $25, 000 in Program funds, per project, not
  to exceed 75% of the total eligible project costandnotto exceed $100,000 in Program
  . funds. Activities may include signage, awning, and painting.
  e  Small Business Assistance
  «The LPA may award between $5,000 - $50,000 in Program funds, per project, not to
  exceed 75% of the total eligible project cost. Small Business Assistance funds may
  be used for permanent machinery and equipment.
  The minimum match requirement is 25% of the total project cost.
  Match requirements must be realized on a building-by-building basis and are calculated using
  the total project cost.
  In-kind match is not eligible.
  Costs incurred prior to the effective date of the grant agreement are not eligible for
  reimbursement and not éligible as a match.
  ©  Soft Costs
  * Eligible soft costs include Architecture, Engineering, and Environmental Testing
  expenses.
  *  Soft costs must be included within per builling activity funding limits identified :
  above and may not exceed 18% of the awarded funds.
  * . Soft costs require matching funds, and in-kindmatch is not eligible.

20250577-- New York Forward (NYF) Schedule B  Page 2 of 9