2517 Long Rd.
  Grand Island, NY 14072

  CHANGE ORDER REQUEST RECAP

  Job Name: Hamburg Senior Community Center  Date:  10/6/2026
  Contract No.: 2025-03E  Change Order Reqest No.: 9-1 REV 2  CIR Job No.:  2502019
Description:
Per RFP-005, CIR to provide new underground electric feed from existing utility pole to existing 150A panel. Electric feed to contain 1 set of
(4) 500 MCM CU & (1) #2 CU in 3-1/2" PVC. Overhead service & (2) 40' utility poles to be removed. CIR to provide (4) light pole bases &
(6) pole mounted fixtures. CIR to provide new underground electric feed to water hot box & sanitary pumps.
Material Description  Material  Labor Description  Hours  Rate  Labor Cost
Attached Accubid Extension  $  60,156.67  Gen. Foreman ST  -  $ 116.29  $  -
Kistner Concrete Quote Dated 9/2/26  $  4,958.00  Foreman ST  196.0  $ 110.12  $  21,583.52
PSG Quote #25-63831-9  $  9,194.00  Journeyman ST  393.0  $  97.78  $  38,427.54
SuperBreakers Quote Dated 9/1/26  $  97.98  $  -
  $  -
  $  -
  $  -
  $  -
  $  -
Material Cost Subtotal:  $  74,406.65  $  -
Job Expenses:  Supervision (12.5%)  73.625  $  -  $  -
Document Control  $  -  Tool Usage (4% of Labor)  $  -
Travel Time Costs  $  -  Total Labor Costs:  $  60,011.06
Transportation  $  -  SUBTOTAL(L+M+JE)  $  134,417.71
Storage / Warehouse  $  -  Research & Layout  0%  $  -
Safety (3% of Labor Cost)  $  -  Material Handling  0%  $  -
Inspections & Permits  $  -  Clean Up Costs:  0%  $  -
Record Drawings  $  -
Fuel Surcharges (4% of Material Cost)  $  -
'26 - '27 Wage Rate Increase  $  -  SUBTOTAL:  $  134,417.71
  Overhead  10%  $  13,441.77
Total Job Expenses  $  -  Profit  5%  $  7,392.97
Qualifications & Clarifications:  Site Work (Tom Greenauer)  $  79,935.00
1.) Sales Tax is NOT included  Subcontractor Mark-up  5%  $  3,996.75
2.) Straight Time only-NO overtime included  TOTAL:  $  239,184.21
3.) All trenches to be sand bed encased  Tax on Total  -  $  -

4.) All additional work is subject to schedule extension  Bond Cost  2%  $  3,587.76

5.) Disposal of 40' utility poles is excluded  Change Order Request Total  $ 242,771.97
  We reserve the right to correct any and all errors and omissions  158