Town of Hamburg
  Board of Zoning Appeals
  June 2, 2026
  Minutes

The Town of Hamburg Board of Zoning Appeals met for a Regular Meeting on Tuesday, June 2,
2026 at 7:00 P.M. in Room 7B of Hamburg Town Hall, 6100 South Park Avenue. Those attending
included Chairman Ric Dimpfl, Vice-Chairman Nicole Falkiewicz, Commissioner Jeff Adrian,
Commissioner Mark Yoder, Commissioner Dennis Chapman, Commissioner Jack Kuebler and
alternate Commissioner Catherine Mika filling in for Commissioner Laura Hahn.

Also in attendance were Code Enforcement Officer Jeffrey Skrzypek and Board of Zoning
Appeals Attorney Joseph Gogan.

Board members recited the Pledge of Allegiance.

Chairman Dimpfl asked for a moment of silence in honor of our active military and those who
have made the ultimate sacrifice.

Chairman Dimpfl pointed out the location of the two (2) fire exits in the room.

Commissioner Hahn read the Notice of Public Hearing.

Application # 6150 Donald Spittler – Requesting one (1) use variance to allow for a tier 3

battery energy storage system at 6433 Railroad Ave (Zoned NC)

Sean Hopkins spoke on behalf of RIC Development LLC. Andrew Welch, Director of
Development for RIC Development appeared too. Both men spoke on behalf of the property
owner Donald Spittler. Hopkins stated that they are not here to ask for a decision tonight
because the project is subject to a state environmental review. On May 20 th, the Planning Board
did adopt a resolution seeking lead agency status, and that 30 day comment period will not
expire until the end of June.

Welch spoke first. RIC Energy is a company that delivers sustainable energy projects to meet
the growing needs of communities. They are headquartered in New York. Most of their projects
have been in New York. They want to build a battery energy storage system at 6433 Railroad
Ave. This land is currently undeveloped, forested, and in between two railroad tracks. It is
zoned Neighborhood Commercial and was previously Industrial. The parcel is approximately 2.6
acres. They want to locate two retail energy projects that are each 5 megawatts; the cabinets
for each of the batteries are 1 megawatt, so each project has 5 cabinets. This will take up about
14,000 sq. ft. total. Each unit is about the size of a fenced in tennis court. These will be
remotely monitored 24 hours a day and have no personnel on site during normal operating
hours. This location connects to an existing distribution line. They are hooking into the local
distribution in the Town and this will provide within the grid of the Hamburg area.