West Seneca Sewer Report | Page 9

Standards and Specifications for Erosion and Sediment Control has been prepared for this
project. The SWPPP is included in the Site Plan Application Package.

Section 5 – Proposed Water Facilities

5.1 Proposed Water Connections

The project is proposing a new water connection to the Eire County Water Authority (EWCA)
12” water main on the north side of Clinton Street.

5.2 Existing Flow Test Data

Existing hydrant flow test data was provided for hydrant J11F55 and completed on 7/15/2019.
The existing water line is a 6” cast iron pipe on the south side of Clinton Street. The residual
pressure was 54 psi at 872 gpm.

5.3 Proposed Water Demand

The anticipated average daily water demand from the proposed development was
calculated using Table B-3 of the NYSDEC Design Standards for Intermediate Sized
Wastewater Treatment Systems, dated March 5, 2014. For apartments constructed after
1994, the average daily water demand per bedroom is 110-gallons per day. The proposed
project includes updating all water fixtures to modern energy efficient fixtures. Based on
this, the anticipated average daily water demand for the proposed development is as
follows:

  Table 7: Anticipated Water Demand
  Average Daily Demand
 No. of Bedrooms  No. of Units  Water Demand Per Unit (GPD)
  (GPD)
  1 Bedroom  24  110  2,640
  2 Bedroom  29  220  6,380
  3 Bedroom  22  330  7,260
  Total Average Daily Demand  16,340
  Maximum Day (2x Average Daily)  32,680
  Peak Hourly (4x Average Daily)  35,360

5.4 Proposed Fire Protection and Backflow

The project is proposing one combined service from Clinton Street, which will split into
combined services feeding the existing mansion and new building respectively. New
backflow prevention devices are proposed for each of the buildings, splitting into separate
domestic and fire services after the backflows. The domestic services will be metered within
each building. The private hydrants on site will be fed after the backflow within each building.
Refer to the MEP and FP plans for detailed design.