TOWN OF ORCHARD PARK
  ENGINEERING  DEPARTMENT
  S 4295 South Buffalo Street  Orchard Park, New York 14127-2609

  Phone:  (716) 662-6425  TOWN ENGINEER
  Email:  [email protected]  WAYNE  L.  BIELER, PE., CFM

June 26, 2026

Honorable Town Board
Town of Orchard Park
4295 South Buffalo Street
Orchard Park, New York 14127

Re:  LaBella Associates, DPC
  Change Order No. 2 - Phase Il Rezoning District Legal Descriptions
  Stadium Area comprehensive Development Plan

Dear Board Members:

As you are aware for the Stadium Area Comprehension Development Plan, LaBella
Associates, DPC was hired to complete a master plan of the area.  Now due to the
current workload of the Orchard Park Engineering Department, LaBella Associates, DPC  .
is requesting additional funds to prepare legal descriptions for the newly created MANY;
BC, and RS zoning districts. The cost of this work is $9,000.00.  Nae
If approved, this change order would increase the Contract amount from $252,700.00 to
$261,700.00, representing an increase of 3.56%.  Fund will be needed to be transferred
to Capital Account AB020 “Stadium Area Comprehension Plan’.

|, therefore, recommend that you adopt the following resolutions:

  1.  The Town Board approve Change Order #2 to the Contract with LaBella
  Associates, DPC, 300 State Street, Rochester, New York 14614 for preparing
  legal descriptions for the newly created  6, BC, and RS zoning districts as a
  part of the Stadium Area Comprehension Development Plan in an amount not to
  exceed $9,000.00.
  2.  Approve the transfer of $9,000 from AD002 “Bussendorfer Drainage” to ABO20
  “Stadium Area Comprehensive Plan’.

Respectfully
  emi  ff

Wayne 4 Bieler, P.E.,CFM  “\.
Town Engineer
Attachment
Cc:  Ed Flynn, LaBella Associates, DPC
  Nichole Ruf, Drescher & Malecki
  File #2024.024

S:\Town Projects\DR-2 Rezoning\Letter to TB Staduim Plan CO #2.doc