Southtowns Record

PBA06.11.2026packet

Government
Town of West Seneca
Board
Planning Board
Meeting
Jun 11, 2026, 6:00 p.m.
Posted by publisher
Jun 3, 2026
Kind
Agenda packet
Topics
Water, sewer and drainage, Housing, Zoning and land use, Roads and traffic, Parks and recreation, Budget and taxes, Public safety

Original document

Same meeting

Text · page 737 of 849

Read the whole document on one page (all 849 pages, each with its own heading)

Part III.A.7.
contractor(s) and subcontractor(s) that will be responsible for constructing the
SMPs included in the SWPPP. The owner or operator must have each of the
contractors and subcontractors identify at least one person from their
company to be trained contractor that will be responsible for implementation
of the SWPPP. The owner or operator must ensure that at least one trained
contractor is on site daily when soil disturbance activities are being
performed.

The owner or operator must have each of the contractors and subcontractors
identified above sign a copy of the following certification statement below
before the commencement of construction activities:

  "I hereby certify under penalty of law that I understand and agree to
  comply with the requirements of the SWPPP and agree to implement any
  corrective actions identified by the qualified inspector during a site
  inspection. I also understand that the owner or operator must comply with
  the requirements of the most current version of the New York State
  Pollutant Discharge Elimination System (SPDES) Construction General
  Permit (CGP) for Stormwater Discharges from Construction Activities and
  that it is unlawful for any person to cause or contribute to a violation of
  water quality standards. Furthermore, I am aware that there are significant
  penalties for submitting false information, that I do not believe to be true,
  including the possibility of fine and imprisonment for knowing violations"

In addition to providing the certification statement above, the certification
page must also identify the specific elements of the SWPPP that each
contractor and subcontractor will be responsible for and include the name and
title of the person providing the signature; the name and title of the trained
contractor responsible for SWPPP implementation; the name, address and
telephone number of the contracting firm; the address (or other identifying
description) of the site; and the date the certification statement is signed. The
owner or operator must attach the certification statement(s) to the copy of the
SWPPP that is maintained at the construction site. If new or additional
contractors are hired to implement measures identified in the SWPPP after
the commencement of construction activities, they must also sign the
certification statement and provide the information listed above prior to
performing construction activities.

  31