Part IV.C.2.d.
  d. For construction sites where soil disturbance activities have been shut
  down with partial project completion, the requirement to have the qualified
  inspector conduct inspections ceases if all areas disturbed as of the
  project shutdown date have achieved final stabilization and all SMPs
  required for the completed portion of the project have been constructed in
  conformance with the SWPPP and are operational. The owner or operator
  must notify the DOW Water (SPDES) Program contact at the Regional
  Office (see contact information in Appendix E) or, in areas subject to the
  review authority of Traditional Land Use Control MS4 Operator(s) in
  accordance with Part I.D.2.b.ii.1., the Traditional Land Use Control MS4
  Operator(s) (provided the Traditional Land Use Control MS4 Operator(s)
  are not the owners or operators of the construction activity) in writing prior
  to the shutdown and again in writing prior to resuming construction
  activity. If soil disturbance activities are not resumed within 2 years from
  the date of shutdown, the owner or operator must terminate coverage by
  meeting the requirements of Part V; or

  e. For construction sites involving soil disturbance of one (1) or more acres
  that directly discharge to one of the 303(d) segments listed in Appendix D
  or is located in one of the watersheds listed in Appendix C, the qualified
  inspector must conduct at least two (2) site inspections every seven (7)
  calendar days. The two (2) inspections must be separated by a minimum
  of two (2) full calendar days.

3. At a minimum, the qualified inspector must inspect:

  a. all erosion and sediment control practices and pollution prevention
  measures to ensure integrity and effectiveness; and

  b. all SMPs under construction to ensure that they are constructed in
  conformance with the SWPPP; and

  c. all areas of disturbance that have not achieved final stabilization; and

  d. all points of discharge to surface waters of the State located within, or
  immediately adjacent to, the property boundaries of the construction site;
  and

  e. all points of discharge from the construction site.

  40

  Page 746 of 849