Part IV.C.4.j.i.
  i. Total area with active soil disturbance (not requiring either
  temporary stabilization or final stabilization); and

  ii. Total area with inactive soil disturbance (requiring either temporary
  stabilization or final stabilization); and

  iii. Total area that has achieved temporary stabilization; and

  iv. Total area that has achieved final stabilization; and

  k. Current stage of construction of all SMPs and identification of all
  construction activity on site that is not in conformance with the SWPPP
  and technical standards; and

  l.  Corrective action(s) that must be taken to install, repair, replace or
  maintain erosion and sediment control practices and pollution prevention
  measures; and to correct deficiencies identified with the construction of
  the SMP(s); and

  m. Identification and status of all corrective actions that were required by
  previous inspection; and

  n. Digital photographs, with date stamp, that clearly show the condition of all
  practices that have been identified as needing corrective actions. The
  qualified inspector must attach color copies of the digital photographs to
  the inspection report being maintained onsite within seven (7) calendar
  days of the date of the inspection. The qualified inspector must also take
  digital photographs, with date stamp, that clearly show the condition of the
  practice(s) after the corrective action has been completed. The qualified
  inspector must attach paper color copies of the digital photographs to the
  inspection report that documents the completion of the corrective action
  work within seven (7) calendar days of that inspection.

5. Within one business day of the completion of an inspection, the qualified
  inspector must notify the owner or operator, and appropriate contractor or
  subcontractor identified in Part III.A.7., of any corrective actions that need to
  be taken. The contractor or subcontractor must:

  a. if the corrective action does not require engineering design:

  42