Part V.A.1.b.
  b. Planned shutdown with partial project completion:

  i. all soil disturbance activities have ceased; and

  ii. all areas disturbed as of the project shutdown date have achieved
  final stabilization; and

  iii. all temporary, structural erosion and sediment control measures
  have been removed; and

  iv. all SMPs required for the completed portion of the project have
  been constructed in conformance with the SWPPP and are
  operational; and

  v. an as-built drawing has been prepared; or

  c. In accordance with Part I.G. Change of Owner or Operator; or

  d. The owner or operator has obtained coverage under an alternative
  general SPDES permit or an individual SPDES permit.

2. For construction activities that require qualified inspector inspections in
  accordance with Part IV.C.1. and have met Part V.A.1.a. or b., the owner or
  operator must have the qualified inspector perform a final site inspection prior
  to submitting the eNOT. The qualified inspector must, by signing the “Final
  Stabilization” and “Post-Construction Stormwater Management Practice(s)”
  certification statements on the eNOT, certify that all the requirements in Part
  V.A.1.a. or b. have been achieved.

3. For construction activities that are subject to the review authority of
  Traditional Land Use Control MS4 Operator(s) in accordance with Part
  I.D.2.b.ii.1. and meet Part V.A.1.a. or b., the owner or operator must have the
  Traditional Land Use Control MS4 Operator(s) sign the “MS4 Acceptance”
  statement on the eNOT in accordance with the requirements in Part VII.J. A
  Traditional Land Use Control MS4 Operator official, by signing this statement,
  determined that it is acceptable for the owner or operator to submit the eNOT
  in accordance with the requirements of this Part. A Traditional Land Use
  Control MS4 Operator can make this determination by performing a final site
  inspection themselves or by accepting the qualified inspector’s final site
  inspection certification(s) when required in Part V.A.2.