29. Submit a complete Notice of Termination form electronically using the NYSDEC eNOT.
  Coverage is terminated as of the termination date indicated in the Letter of Termination (LOT),
  which is sent by NYSDEC after a complete eNOT is submitted.

  30. Request and receive all SWPPP records from the Owner’s/Operator’s Engineer and archive
  those records, along with the LOT, for a period of at least five (5) years from the date that
  NYSDEC accepts a complete NOT submitted.

  31. Implement the Post-Construction Inspections and Maintenance procedures outlined in
  Appendix G.

  32. The Owner/Operator must keep the SWPPP current so that it at all times accurately documents
  the erosion and sediment controls practices that are being used or will be used during
  construction, and all post-construction stormwater management practices that will be
  constructed on the site. At a minimum, the Owner/Operator shall amend the SWPPP, including
  construction drawings:
  a) Whenever the current provisions prove to be ineffective in minimizing pollutants in
  stormwater discharges from the project site;
  b) Whenever there is a change in design, construction, or operation at the construction
  site that has or could have an effect on the discharge of pollutants; and
  c) To address issues or deficiencies identified during an inspection by the “Qualified
  Inspector,” the Department, or other Regulatory Authority.
  d) To document the final construction conditions.
  33. When property ownership changes or when there is a change in operational control over the
  construction plans and specifications, the original owner or operator must notify the new owner
  or operator, in writing, of the requirement to obtain permit coverage by submitting a NOI with
  the Department, in conformance with Part I.G.. For construction activities subject to the
  requirements of a regulated, traditional land use control MS4, the original owner or operator
  must also notify the MS4, in writing, of the change in ownership at least 30 calendar days prior
  to the change in ownership.

 7.2 Owner’s/Operator’s Engineer’s Responsibilities

  1. Prepare the SWPPP using good engineering practices, best management practices, and in
  compliance with all federal, state, and local regulatory requirements.

  2. Prepare the electronic Notice of Intent (eNOI) (see Appendix B) and sign the “SWPPP Preparer
  Certification Form.” Forward the Owner/Operator Certification Form to the Owner/Operator for
  signature.

  3. Provide copies of the SWPPP to the Town of West Seneca once all signatures and attachments
  are complete.

  4. Enter Contractor’s information in Section 7.5 “SWPPP Participants” once a Contractor is
  selected by the Owner/Operator.

  5. Participate in a pre-construction meeting which shall include the Town of West Seneca
  representative, Owner/Operator, Qualified Inspector, Contractor, and all subcontractors to
  discuss responsibilities as they relate to the implementation of this SWPPP.

Stormwater Pollution Prevention Plan
  Page 29