BR Ponding Area
Examine the entire Bioretention surface and side slopes

Problem (Check if Present)  Follow-Up Actions

    Try filling the eroded areas with clean topsoil or sand, and cover with
  mulch.
    If the problem recurs, you may have to use stone (e.g., river cobble) to fill
  in problem areas.
    If the erosion is on a side slope, fill with clay that can be compacted and
  seed and mulch the area.
    Other:

  There is erosion in the bottom or on the side
  slopes. Water seems to be carving out rills as
  it flows across the Bioretention surface or on
  the slopes, or sinkholes are forming in certain    Kick-Out to Level 2 Inspection: The problem persists or the erosion is more
  areas.  than 3-inches deep and seems to be an issue with how water enters and
  Source: Stormwater Maintenance, LLC.  moves through the Bioretention cell.
    Kick-Out to Level 2 Inspection: The problem does not seem to be caused
  by flowing water, but a collapse or sinking of the surface (e.g., “sinkhole”)
  due to some underground problem.

    If the problem is minor (just small, isolated areas are not covered with
  water), try raking the surface OR adding mulch to low spots to create a
  more level surface. You may need to remove and replace plantings in
  order to properly even off the surface.
    Check the surface with a string and bubble level to get the surface as flat
  as possible.
    Other:

    Kick-Out to Level 2 Inspection: Ponding water is isolated to less than half
  The bottom of the Bioretention cell is not flat,
  of the Bioretention surface area, and there seem to be elevation
  and the water pools at one end, along an
  differences of more than a couple of inches across the surface.
  edge, or in certain pockets. The whole bottom
  is not uniformly covered with water. See
  design plan to verify that bioretention surface
  is intended to be flat. Check during or
  immediately after a rainstorm.

  Page 5 of 8