Southtowns Record

SUPPORTING DOCUMENTS 2A-5C3

Government
Town of Aurora
Board
Town Board
Meeting
Oct 26, 2026
Kind
Agenda packet
Topics
Audits and oversight, Budget and taxes, Public safety, Roads and traffic, Water, sewer and drainage

Original document

Same meeting

Text · page 8 of 101

Read the whole document on one page (all 101 pages, each with its own heading)

This document was a scan. Its text was produced by character recognition and may contain errors; check the original for exact wording.

Lease Agreement (B), correct such Pre-Existing Condition, or authorize the Town’s contractor to
correct it at the Village’s cost, in either case within a time frame that does not delay the Project.
Any delay or added cost to the Project resulting from the Village’s failure to timely address a Pre-
Existing Condition shall be borne by the Village.

4. PROCUREMENT AND PERFORMANCE OF THE WORK
4.1 The Town shall act as “Owner” under the construction contract and all other contracts for the
Project and shall be solely responsible for the procurement, award, administration and payment of
such contracts. The Village shall not be a party to any such contract and shall have no liability
thereunder.  :
4.2 The Town shall cause the Project to be procured and performed in compliance with all
applicable laws, including, without limitation, Section 103 of the General Municipal Law. The
Town shall cause its contractors to obtain all required building permits and approvals from the
authority having jurisdiction.
4.3 The Town shall require its general contractor to furnish a performance bond and a payment
bond, each in a penal sum of one hundred percent (100%) of the contract price, issued by a surety
authorized to do business in the State of New York.  |
4.4 The Town shall use good faith efforts to cause the Project to achieve substantial completion
within the contract time established in the construction contract, and shall keep the Village
Representative reasonably informed of the Project schedule. The Town shall have no liability to
the Village for delays in the Project caused by its contractors, unforeseen conditions, or other
causes beyond the Town’s reasonable control.

5. HAZARDOUS MATERIALS
5.1 Prior to commencement of any demolition or construction work, the Town shall, at its sole
cost, cause an asbestos survey of all areas to be disturbed by the Project to be performed by a firm
and personnel holding the licenses and certifications required by Article 30 of the Labor Law and
12 NYCRR Part 56 (industrial Code Rule 56), and shall provide a copy of the survey report to the
Village.
5.2 If asbestos-containing materials or other hazardous materials are identified in the Project area,
the Town shall, at its sole cost, cause such materials to be abated, handled and disposed of by duly
licensed contractors in compliance with all applicable federal, state and local laws, including air
monitoring and clearance testing where required. The Town shall coordinate any abatement work
with the Village so as to protect the occupants of the Building.
5.3 Nothing in this  Agreement shall make the Town responsible for hazardous materials located
outside the areas disturbed by the Project, or for conditions that are not disturbed or exacerbated
by the Project, all of which shall remain the responsibility of the Village as owner of the Building.
Ifhazardous materials outside the Court Premises must be abated to perform the Project, the Parties
shall confirm in writing the allocation of such cost prior to the abatement work.
6. ACCESS, COORDINATION AND OCCUPIED BUILDING
6.1 The Village grants to the Town, the Architect, and the Town’s contractors and their
subcontractors a license to enter the Building and the surrounding parking lot for the purposes of

  3