Section 1 - Location & Description

This project consists of the first phase of the redevelopment of the approximately 56 acre former Seneca
Mall property, located within the area bounded by Slade Avenue, Ridge Road, and Orchard Park Road in the
Town of West Seneca. The proposed redevelopment includes construction of an approximately 158,000
square foot commercial building to be occupied by Costco Wholesale, along with associated parking,
utilities, stormwater management facilities, and other supporting site improvements. This phase also
includes the primary infrastructure necessary to accommodate future phases and the ultimate full build out
of the redevelopment site.

Proposed site improvements include upgrades to the existing utility infrastructure, construction of a new
internal roadway network, parking facilities, site lighting, landscaping, and stormwater management
system designed for the full build out. These improvements are intended to provide the framework required
for future development throughout the remainder of the property.

The project site is currently occupied by the remnants of the former Seneca Mall and the existing Tops
Market grocery store. The Tops Market will remain operational throughout construction and will not be
impacted by the proposed redevelopment. Construction activities associated with the redevelopment are
expected to result in approximately 27.71 acres of land disturbance.

Section 2 - Water Service

Water service for the proposed Seneca Mall redevelopment will be provided by a new private 8-inch
combined water service main connected to an existing 24-inch Erie County Water Authority (ECWA) water
main located within the northbound travel lane of Slade Avenue. The proposed water distribution system
will consist of 8 & 10-inch AWWA C900 water main and will be designed to accommodate both domestic
water demand and fire protection requirements for the development. Proposed and future buildings within
the redevelopment will be served by separate 6-inch polyethylene combined water services connected to
the proposed private water main system. The water distribution infrastructure has been designed to
support the phased development of the site while providing adequate domestic and fire flow capacity for
the ultimate build out condition.

The proposed 8-inch water main will extend into a dedicated insulated enclosure housing the water meter
and backflow prevention equipment. This enclosure will contain a reduced pressure zone (RPZ) backflow
preventer and will be heated to prevent freezing during winter conditions.

Discharge resulting from RPZ testing, maintenance, or relief valve operation will be conveyed by gravity to
the nearest drainage inlet. The property owner will be responsible for maintaining the drainage conveyance
system and ensuring that all drainage ports remain free of snow, ice, and debris to allow proper operation.
Water service within the apartment buildings will be utilized for typical domestic purposes, including
potable water supply and fire protection.

Four private hydrants will be installed on site as part of the development to ensure fire hose coverage not
exceeding 400’.

Domestic Summary:
Peak Operating Demand:  168.38 gpm
Water Main:  24” on Slade Avenue
Static Pressure:  90 psi (Per ECWA)
Friction Loss:  0.0 psi
Loss through meter/RPZ:  13 psi
Elevation Loss:  12.99 psi
Pressure after RPZ:  77.0 psi

Repairs to all devices will be made during off hours, dual backflow preventers are not required. The site is
not located in a 100-year flood plain. Disinfection of the water service following installation will be
continuous feed, according to AWWA C-651, latest revision.