CARMINA WOOD DESIGN  Project No.:  24-4113  Date:  7/13/2026
  80 SILO CITY ROW, SUITE 100  Project Name:  West Seneca Exchange
  BUFFALO, NEW YORK, 14203  Project Address:  Orchard Park Road West Seneca, NY
  (716) 842-3165  Subject:  Sanitary Sewer & Water Demand Calcs
  FAX (716) 842-0263  Sheet:  3  of  3

Water Demand Calculations (domestic):

  Proposed Shopping Center Development

  61,228 gpd  x  1.1  =  67,350 gpd  *use 110% of sewage demand

  *use 1.8 peaking factor and assume a 12 hour day

  67,350  gpm  x  1day/12hr  x  1hr/60min  =  93.54 gpm

  93.54  gpm  x  1.8  =  168.38 gpm  Qpeak
  Headlosses:
  Qpeak =  168.38 gpm
  Pipe  =  8 inch Polyethylene  C  = 140
  Length =  50 LF (approx. distance from tap to RPZ)
  10.44 L Q1.85  10.44(50)(27.89) 1.85
  HL =  1.85  4.866  =  =  0.03  ft  =  0.01  psi
  C D  (140)1.85 (8)4.866
  Δ elev =  0 ft =  0.00 psi
  Loss through meter  =  1 psi
  Loss through RPZ  = 12 psi
  Total Losses =  13.0 psi
  Static Pressure  =  90 psi  (per ECWA)
  Residual Pressure Following RPZ  =  40 - 13.0  =  77.0 psi  (available after rpz & meter)

  Residual Pressure 30" above 2nd Floor
  Δ elev = 15 ft =  6.50 psi
  Residual Pressure 30" above 2nd Floor  =  70.5  psi *

Water Demand Calculations (fire):

  Proposed Shopping Center Development

  Q=  1,000 gpd

  Headlosses:
  Qpeak =  1168 gpm
  Pipe  =  10 inch C-900 PVC  C  = 140
  Length =  1,300 LF (approx. distance from RPZ to farthest hydrant)
  10.44 L Q1.85  10.44(1300)(1168)
  1.85
  HL =  1.85  4.866  =  1.85  4.866  =  9.36  ft  =  4.05 psi
  C  D  (140)  (8)

  Δ elev =  4 ft  =  1.73 psi

  Static Pressure after RPZ  =  77.0  psi
  Residual Pressure at hydrant  =  77 - 5.8  =  71.2 psi

  Page 685 of 1174