5.5 Construction Housekeeping Practices

 During the construction phase, the Contractor(s) will implement the following measures:

 5.5.1  Sediment Sweeping/Vacuuming

 Any sediment that is tracked by construction vehicles or erosion onto adjacent public or private
 impervious surfaces must be swept or vacuumed, utilizing self-propelled and/or walk-behind
 equipment, and removed on a daily basis. Kick brooms and sweeper attachments are not an
 acceptable means of sweeping. Sweeping or vacuuming should not take place while tracked sediment
 is wet. If tracked sediment is compacted, the sediment must be scraped loose prior to sweeping or
 vacuuming.

 5.5.2  Material Stockpiles
 Material resulting from clearing and grubbing operations that will be stockpiled on-site, must be
 adequately protected with downgradient erosion and sediment controls.

 5.5.3  Equipment Cleaning and Maintenance
 The Contractor(s) will designate areas for equipment cleaning, maintenance, and repair. The
 Contractor(s) and subcontractor(s) will utilize those areas. The areas will be protected by a temporary
 perimeter berm.

 5.5.4  Detergents
 The use of detergents for large-scale washing is prohibited (i.e., vehicles, buildings, pavement
 surfaces, etc.)

 5.5.5  Spill Prevention and Response
 A Spill Prevention and Response Plan shall be developed, for the pollutants identified in Section 5.3,
 for the site by the Contractor(s) that addresses the following:
  1.  Reducing chance of spills
  2.  Stopping the source of spills
  3.  Containing and cleaning up spills
  4.  Disposing of materials contaminated by spills
  5.  Training personnel responsible for spill prevention/response
  6.  Material handling procedures
  7.  Material storage requirements
 The plan shall detail the steps required in the event of an accidental spill and shall identify contact
 names and phone numbers of people and agencies that must be notified.

 The plan shall include Safety Data Sheets (SDS) for all materials to be stored on-site. All workers on-
 site will be required to be trained on safe handling and spill prevention procedures for all materials
 used during construction. Regular tailgate safety meetings shall be held and all workers that are
 expected on the site during the week shall be required to attend.

 5.5.6  Concrete Washout Areas
 A temporary concrete washout area shall be provided for every project where concrete will be poured
 or otherwise formed on-site and shall consist of an excavated or above-ground lined construction pit

Stormwater Pollution Prevention Plan
  Page 21
2241067