personnel will be instructed in these practices by the job site superintendent, who will also be
  responsible for seeing that these practices are followed.

  D.  Product Specific Practices

  The following product specific practices will be followed on the job site.

  1.  Petroleum Products

  All onsite vehicles will be monitored for leaks and receive regular preventative
  maintenance to reduce the chance of leakage. Petroleum products will be stored in
  tightly sealed containers which are clearly labeled. Any petroleum storage tanks stored
  onsite will be located within a containment area that is designed with an impervious
  surface between the tank and the ground. The secondary containment must be
  designed to provide a containment volume that is equal to 110% of the volume of the
  largest tank. Drip pans shall be provided for all dispensers. Any asphalt substances
  used onsite will be applied according to the manufacturer's recommendations. The
  location of any fuel tanks and/or equipment storage areas must be identified on a plan
  by the contractor once the locations have been determined.

  2.  Fertilizers

  Fertilizers will be applied only in the minimum amounts recommended by the
  manufacturer. Once applied, fertilizer will be worked in the soil to limit exposure to
  stormwater. Storage will be in a covered shed. The contents of any partially used bags
  of fertilizer will be transferred to a sealable plastic bin to avoid spills.

  3.  Paints, Paint Solvents, and Cleaning Solvents

  All containers will be tightly sealed and stored when not in use. Excess paint and
  solvents will not be discharged to the storm sewer system but will be properly disposed
  of according to manufacturer's instructions or state and federal regulations.

  4.  Concrete Wastes

  Concrete trucks will be allowed to wash out or discharge surplus concrete or drum wash
  water on the site, but only in either (1) specifically designated diked areas which have
  been prepared to prevent contact between the concrete and/or wash out and storm
  water which will be discharged from the site or (2) in locations where waste concrete
  can be poured into forms to make riprap or other useful concrete products.

  The hardened residue from the concrete wash out diked areas will be disposed of in the
  same manner as other non-hazardous construction waste materials or may be broken up
  and used on site as deemed appropriate by the Contractor. The job site superintendent
  will be responsible for seeing that these procedures are followed.

  All concrete wash out areas will be located in an area where the likelihood of the area
  contributing to storm water discharges is negligible. If required, additional BMPs must
  be implemented to prevent concrete wastes from contributing to storm water
  discharges. The location of concrete wash out area(s) must be identified on a plan by
  the contractor once the locations have been determined. In addition, a standard detail
  on the construction of the concrete wash out shall be included on this plan.

  E.  Solid and Construction Wastes

West Seneca Exchange
07/20/2026
Page 21 of 24