Southtowns Record

PBM 8.13.26 FINAL

Government
Town of West Seneca
Board
Planning Board
Meeting
Aug 13, 2026, 6:00 p.m.
Posted by publisher
Oct 1, 2026
Kind
Minutes
Topics
Zoning and land use, Water, sewer and drainage, Roads and traffic, Public safety, Budget and taxes

Original document

Same meeting

Text · page 4 of 6

o  Parcel/Site Details: The Tops store remains; Tops Express, Community Bank,
  and Lorigo Law Offices are not part of the development. The rear of the Costco
  site abuts a railroad.
  o Traffic Improvements: The developer will fund significant off-site
  improvements, including replacing two traffic lights, adding a third on Slade
  Avenue, widening Slade Avenue with a center turn lane and sidewalks, and
  reconfiguring the Ridge Road/Slade Avenue/US-219 off-ramp. A right-in only
  driveway from Slade Avenue will serve Costco.
  o Stormwater & Sewer: A sewer capacity analysis was approved by the Town.
  Stormwater will discharge via a 6 ft x 6 ft NYSDOT-owned pipe that crosses
  Orchard Park Road through the Wegmans lot to a creek. This pipe was televised
  for inspection. All private sewer mains on the property will be replaced to
  eliminate I&I, and an I&I fee will be paid to the Town.
  o Geotechnical: A large on-site soil pile will be used to surcharge (compress) the
  soil under the Costco and fuel facility pads for structural stability. This process is
  expected to take 4-12 months. The soil will be redistributed on-site afterward.
  o Costco Specifics: The building includes a main retail area and a Market Delivery
  Option (MDO) area for local delivery. It will have a Tire Center (sales/installation
  only). The fuel facility will have 16 pumps (32 stations) with long hoses, ~145
  feet of queuing space, an attendant, and digital signage. Truck circulation is
  designed to keep delivery vehicles away from the main customer entrance. Seven
  new fire hydrants and a fire protection loop are proposed.
  o Utilities & Landscaping: The site will have separate utility services.
  Landscaping will exceed town standards with native species and full-site
  irrigation. Lighting will be modern, dark-sky compliant LED.
  o Timeline: The team is targeting a Q2 2027 start for site work, with pad delivery
  to Costco by end of 2027/early 2028. Once Costco begins, development is
  expected to accelerate. Offsite traffic is part of the initial phase.
•  Board Questions and Answers:
  o Joseph Sherman asked if equipment could accelerate soil compression.
  ▪ Response: Surcharging was deemed most effective; will take 4-12
  months.
  o James Frick asked about the discharge pipe ownership.
  ▪ Response: It's owned by NYSDOT and crosses the Wegmans lot to the
  creek. If over 5 ft, the state must inspect it every six years.
  o Tim Hayes asked about the timeline.
  ▪ Response: Surcharging can occur in winter (~4 months); target site work
  start Q2 2027.
  o Margaret Bebak asked for specifics on Slade Avenue improvements.
  ▪ Response: Widening, center turn lane, sidewalks, and new/upgraded
  signals, all paid by the developer. The traffic consultant performed
  analysis, and the design was iterated per County/DOT reviews, who are
  comfortable with it.