Copied word for word from these minutes. Who moved and seconded, the tally and the roll call appear only where the minutes state them. Picked out automatically: the minutes themselves are the record. All votes for this government.

  1. none. On a motion from Szustakowski, seconded by Root, the minutes were approved as submitted. Carried 3 ayes, 0 noes, 0 absent.

    Carried, 3–0 · Moved by Szustakowski, seconded by Root

    Page 1 of the minutes, motion 1

  2. plan. Mrs. Ballou moved on to the planning review and recommendations. Some of the items covered in this review were visual compatibility with the area, written confirmation regarding lighting and questions regarding agricultural resources such as prime farmland overlay. Mrs. Ballou also briefly explained the SEQRA process. Chairman Wilkins asked for an explanation of the prime farmland overlay. Planning member Root expressed concerns about landscaping, fire protection concerns and storm drainage details. Chairman Wilkins opened the floor to questions from the public that had signed in to speak. The first to speak was Chaffee Sardinia Fire Chief Ronald Kenyon who asked questions about what…

    Carried, 3–0 · Moved by Root, seconded by Szustakowski

    Page 2 of the minutes, motion 2 (full wording); vote on page 3, motion 2

Text · page 1 of 3

Read the whole document on one page (all 3 pages, each with its own heading)

TOWN OF SARDINIA PLANNING BOARD MEETING
  MINUTES

  August 24, 2026

Members Present:
Ryan Wilkins – Chairman
Aaron Root
Dan Szustakowski

Absent:

Also Present:
Town Clerk Jennifer Bray
Taylor Erhardt – DiMatteo Roach & Kelly
Nina Ballou - Wendel
Approx. 60 Guests

Chairman Wilkins called the August Planning Board meeting to order at 7:00 PM. After welcoming
everyone Chairman Wilkins introduced the members of the Planning Board. Mr. Wilkins stated that
Nexamp would be giving a presentation on a proposed Battery Energy Storage System on Genesee Rd.
and asked that everyone hold their questions until the end of the meeting.

Old Business –

Chairman Wilkins asked if there were any issues with the minutes from the July meeting. There were
none. On a motion from Szustakowski, seconded by Root, the minutes were approved as submitted.
Carried 3 ayes, 0 noes, 0 absent.

New Business –

Chairman Wilkins welcomed representatives from Nexamp and Environmental Design Partnership (EDP)
that were in attendance to do a presentation for a proposed Battery Energy Storage System to be know
as Sardinia East LLC and will be located on a portion of a parcel at 10599 Genesee Rd. It was noted that
Nina Ballou from Wendel would be arriving late and that Taylor Erhardt from DiMatteo, Roach and Kelly
was in attendance to work on and review this project on the Towns behalf. Chairmen Wilkins gave a brief
summary of the minutes from July and the information presented at that meeting.

Before beginning the presentation Michael DeAngelo, Manager of Business Development for Nexamp,
introduced himself along with Dan Murray, Hazardous Materials Team Chief and Benjamin Wilson, Project
Manager at EDP. Mr. DeAngelo began his presentation with a brief company history including a brief
overview of the number of other projects they have done. He explained that they are a vertically
integrated solar energy and storage company headquartered in Chicago and Boston meaning that they
develop, manage & maintain the projects that they do. Mr. DeAngelo explained that the proposed project
is a stand-alone battery energy storage system with 6 megapack battery units that take energy in during
times of low demand for use during times of high demand to keep the supply of power even. Mr.
DeAngelo stated that the project would take up less than an acre during construction and when finished
will be about a quarter of an acre.

Mr. Murray began presenting the safety aspects of the project and battery energy systems. He explained
that in the event that there is a safety issue such as fire a subject matter expert would be immediately on