Southtowns Record

Supporting Documentation

Government
Town of Orchard Park
Board
Town Board
Meeting
Nov 4, 2026
Kind
Agenda packet
Topics
Parks and recreation, Budget and taxes, Water, sewer and drainage, Roads and traffic, Zoning and land use, Public safety

Original document

Same meeting

Text · page 6 of 37

Read the whole document on one page (all 37 pages, each with its own heading)

This document was a scan. Its text was produced by character recognition and may contain errors; check the original for exact wording.

e  Appropriate crosswalks, signage, markings, and, where warranted, traffic calming or crossing
  treatments shall be provided.
121.86 Structures
Trail related bridges, boardwalks, railings, retaining walls, and similar structures shall be designed to applicable
engineering and safety standards and be suitable for expected loads and environmental conditions and Town
adopted Standards.

Easements, Dedication, and Ownership

121.87 Trail Easements
Public trail easements shall:

  e  Be shown and labeled on preliminary and final subdivision plat plans and drawing sets.

  e  Include sufficient width to accommodate the trail, shoulders, maintenance access, and vegetation
  management.

  e  Grant the Town of Orchard Park the right to construct, maintain, repair, and regulate public use of the
  trail.

121.88 Dedication of Land
Where the Planning Board determines that dedication is appropriate, trail corridors and associated land may be
dedicated as public right-of-way or parkland as a condition of subdivision approval.

121.89 Ownership and Maintenance
The Planning Board shall determine whether trails will be owned and maintained by the Town, a homeowners’
association, or another approved entity, and such responsibilities shall be documented in recorded agreements.

Construction, Inspection, and Acceptance

121.90 Construction Timing
Trail construction shall be completed prior to issuance of final occupancy permits for the phase of the
subdivision in which the trail is located, unless the governing body approves an alternative phasing plan and
associated financial security.
121.91 Inspections
The municipality Town of Orchard Park Engineering Department or its designee shall have the right to inspect
trail construction at reasonable stages, including subgrade, base, surface, and final completion.

121.92 Acceptance
Upon satisfactory completion and inspection, the municipality shall accept dedicated trails or easements for
public use or approve final acceptance by a homeowners’ association or other owner, as applicable.

Fee-in-Lieu and Alternatives

121.93 Fee-in-Lieu
Where physical construction of a trail segment is infeasible or not immediately warranted, the Town Board may,
at its discretion, accept a fee-in-lieu of construction, to be deposited into a dedicated fund for trail acquisition,
design, and construction.  ‘

121.94 Off-Site Improvements
In lieu of on-site trail construction, the Planning Board may allow or require the developer to construct or
improve off-site trail segments that better achieve network connectivity and public benefit, subject to
agreement.

Modifications

121.95 Modifications