TO:  Honorable Town Board
FROM:  Jason Foote, Town Engineer
DATE:  August 24, 2026
SUBJECT:  Town Engineer re Transit Road water main project update

Requested Action:  The Erie County Water Authority (ECWA) recently contacted the Town
  regarding a proposed change to the location of the new meter vault
  and water system interconnection on Transit Road. The meter vault
  and water main crossing were originally proposed to be located
  immediately north of the new bridge over Cazenovia Creek; however,
  the improvements will now be relocated further north near the Kwik Fill
  gas station. In addition, the revised design will include a master
  pressure reducing valve (PRV) within the meter vault, in lieu of
  requiring each individual property owner to install a smaller PRV on
  their water service within their home. The master PRV was not
  included in the original project estimate, and its addition requires a
  larger vault and associated modifications to the proposed
  improvements.

  The original project cost was estimated at approximately $191,000;
  however, as a result of the revised location, larger vault, and addition
  of the master PRV, the updated project cost is estimated at
  approximately $267,000. Fund balance from Water District No. 1 was
  planned to be used to fund the project. Therefore, the increased
  project cost will require approximately $76,000 in additional funding
  from the Water District No. 1 fund balance.

  The work is currently anticipated to be completed sometime in
  September 2026. Once the construction schedule is finalized and the
  project gets closer to construction, I plan to provide letters to the
  affected residents notifying them of the upcoming work and anticipated
  schedule.

RESOLUTION:

ATTACHMENTS: