Southtowns Record

May 20 2026 Town Board Agenda Packet

Government
Town of Evans
Board
Town Board
Meeting
May 20, 2026
Kind
Agenda packet
Topics
Water, sewer and drainage, Roads and traffic, Housing, Budget and taxes, Audits and oversight, Public safety, Parks and recreation

Original document

Same meeting

Text · page 16 of 30

Read the whole document on one page (all 30 pages, each with its own heading)

This document was a scan. Its text was produced by character recognition and may contain errors; check the original for exact wording.

“a thay Wits \e  C&S Companies
  jue  ‘  141 Elm Street, Suite 100
  Buffalo, NY 14203
  p: (716) 847-1630
  f: (716) 847-1454
  WWW.CSCOS.COM

April 9, 2026

William Smith
Director of Planning and Community Development
Town of Evans
8787 Erie Road
Angola, NY 14006

Re:  Water Main Replacement along Lake Shore Road
  Supplemental Agreement 01

Dear Bill:

Several out of scope work items were identified on the design of Phase 2 of the water main replacement
project (AJ Schmidt Elementary School to just south of Lake Street). C&S is submitting this
supplemental agreement request for your consideration to cover the following items:

Water Main Profiles
The original scope did not include water main profiles. After review of the Phase 1 plans, ECWA advised
water main profiles would be required. C&S absorbed the additional time for this work on Phase |
however, we are not able to absorb this cost on Phase 2. The following hours were required to address this
task:

  Staff  Title  Hours  Loaded Rate  Subtotal
  David Askinazi  Managing Engineer  4  $201.78  $807.12
  Chad Stevens  Project Engineer  12  $150.75  $1,809.04
  Kyle Wishman  Engineer  40  $138.63  $5,545.28
  $8,161.43

 Stand-Alone Project
 The original scope assumed the water main work on Phase 2 would be included in the Evans Shoreline
 Trail, Beaches Section (PIN 5764.69) project as a separate share. Given procedural delays and the desire
 to complete some construction in 2026, the decision was made to break out the water main work into a
 stand-alone job. This required preparing a complete set of plans including additional notes, details, tables
 (for temporary restoration) and a re-design of several sections of water main to avoid any ROW
 acquisitions (which would not have been secured before the project was bid). In addition, a separate
 water main specific spec book was prepared. The following hours were required to address these tasks:

  Staff  Title  Hours  Loaded Rate  Subtotal
  Dan Borez  Department Manager  6  $243.41  $1,460.47
  David Askinazi  Managing Engineer  12  $201.78  $2,421.35
  Chad Stevens  Project Engineer  32  $150.75  $4,824.10
  . Kyle Wishman  Engineer  60  $138.63  $8,317.92
  $17,023.84
 Total supplemental agreement request: $25,000

 The Engineer’s Estimate for the Phase 2 water main work stands at $3,550,000. The C&S
  design fee of
 $102,000 is only 2.9% of the anticipated construction cost.