Southtowns Record

April 15 2026 Town Board Agenda Packet

Government
Town of Evans
Board
Town Board
Meeting
Apr 15, 2026
Kind
Agenda packet
Topics
Zoning and land use, Public safety, Budget and taxes, Housing, Water, sewer and drainage, Audits and oversight

Original document

Same meeting

Text · page 27 of 29

Read the whole document on one page (all 29 pages, each with its own heading)

This document was a scan. Its text was produced by character recognition and may contain errors; check the original for exact wording.

Evans Parks and Sturgeon Point Marina Master Plan

Resolution — Change Order #5 (Design and Engineering Services of the Sturgeon Point Phase IIA
Construction Documents)

WHEREAS, the Town of Evans, through a competitive Request for Proposals process, contracted
with Fisher Associates to develop the Evans Parks and Sturgeon Point Marina Master Plan and
Revitalization Study (the “Master Plan”); and

WHEREAS, as part of the Master Plan, Fisher Associates developed a detailed concept plan
reimagining Sturgeon Point Marina as an active, year-round recreational and tourism destination
within a walkable, mixed-use hamlet area, organized for phased implementation; and

WHEREAS, Phase IIA of the Master Plan includes establishing new roadways, walkways, park
spaces, maintenance facilities, parking areas, and the creation of future mixed-use development
sites; and

WHEREAS, Fisher Associates has assisted in securing funding to develop 90% construction
documents for the implementation of Phase IIA of the Master Plan in the amount of $356,250
from NYS Department of State’s Local Waterfront Revitalization Program with an additional
$118,750 from the Town for a total project cost of $475,000; and

WHEREAS, Fisher Associates is able to provide specialized professional engineering and
architectural services for improvements to the Evans Parks system based on their expertise,
project background and local knowledge from continued development and implementation ofthe
Master Plan; and

WHEREAS, Fisher Associates has provided Change Order Request #5 dated March 27, 2026 .in the
amount of $475,000 to provide additional design development and permitting support services
for Phase IIA of the Sturgeon Point Marina Master Plan, progressing the project to approximately
90% Construction Documents;

NOW THEREFORE BE IT RESOLVED that the Evans Parks & Sturgeon Point Master Plan
Change Order Request #6 in the amount of $475,000 is hereby approved.

ROLL CALL VOTE: