6. Capacity Analysis

6.1 Existing 4″ PVC service connection
Full-flow capacity of the 4″ PVC service (n = 0.013) at the minimum building-sewer slope of 1/8″ per foot (S =
0.0104 ft/ft):

 Diameter / area / R  4″ (0.333 ft); A = 0.087 ft²; R = 0.083 ft

 Full-flow capacity  ≈ 0.19 cfs = 87 gpm = 126,000 gpd

 Velocity (full)  2.2 ft/s (≥ 2.0 ft/s minimum ✓)

Peak demand of ≈ 2.0 gpm is about 2% of the 4″ service’s minimum full-flow capacity. The existing service has
ample excess capacity, with more than 85 gpm to spare. At a steeper (typical) slope of 1/4″ per foot the
capacity rises to ≈ 123 gpm.

6.2 Existing 15″ public sewer main
At the minimum design slope for a 15″ sewer (S = 0.15%), and using a conservative lined effective diameter (n
= 0.011), the 15″ main’s full-flow capacity is on the order of:

 Full-flow capacity (minimum slope, conservative)  ≈ 1,100 gpm ≈ 1.6 MGD

 Velocity (full)  ≥ 2.0 ft/s ✓

The 15″ main already conveys the facility’s current flow as part of a much larger tributary area. Because the
project adds no sanitary demand, it places no additional load on the main. Even at the conservative
minimum-slope capacity above, the facility’s peak demand is a negligible fraction (well under 1%) of the
main’s capacity.

7. Conclusions
  ●  No increase in sanitary demand. The addition adds building area only; occupant loads and
  operations are unchanged, so demand remains ≈ 730 gpd average / ≈ 2.0 gpm peak.
  ●  4″ service is adequate. Minimum full-flow capacity ≈ 87 gpm; peak demand uses ≈ 2%, leaving
  substantial excess capacity.
  ●  15″ main is adequate. Capacity on the order of 1,100+ gpm; the main already conveys the facility’s
  flow and receives no additional load from this project.
  ●  No upgrade required. The existing 4″ service and 15″ public main have adequate capacity for the
  facility as proposed.

Appendix A — Representative Unit Design Flow Rates
Representative values for occupancy-based estimating, consistent with the referenced standards.