Cost estimates from CPL’s 2020 Engineering Report At the $10.6 million original cost estimate – this is what the new debt was estimated as per parcel per year for 30 years assuming a 3% interest rate Still not even half of what is anticipated Currently Water District 1 pays about $67/year ($23 maintenance + $44 capital) on a house with assessed value of $150,000 (slide #47) 2026 Budget doubles the Capital rate and will raise the cost on a house with assessed value of $150,000 to $110/year ($23 maintenance + $89 capital) 125