Text · page 149 of 159
Read the whole document on one page (all 159 pages, each with its own heading)
New Projects Town Hall Generator Town Hall Front Entryway • Allocated $91,032 from 2022 excess • Needs full replacement of stairs, sales tax handrails, and pillars • Engineering cost should total $20,000 • Engineering cost = $17,600 • Bid Awarded 9/20/23 for $222,400 • Project still in design stage Tennis Courts Boys & Girls Club Driveway • Needs Resurfacing • Needs pothole repairs • Needs new fence • Needs to be re‐paved • Interest in adding pickleball lines • Interest in adding a practice wall Drainage Improvement Area (Town‐Wide) • Drainage Study performed in 2021 • Drainage Reserve Fund Established • Looking at opportunities to improve drainage through Town 160